Spriggs Farm
Spriggs Farm is an operational 12 MW solar farm in Uttlesford, generating since 30 June 2013. Planning permission was granted on 17 January 2013, 2 months after submission. Operator of record: Abic.
Planning and build timeline
| Application submitted | 8 November 2012 |
| Permission granted | 17 January 2013 2 months after submission |
| Operational | 30 June 2013 5 months after consent |
Screening a site of your own?
Uttlesford approves 89% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Spriggs Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Uttlesford’s record on solar
Uttlesford has decided 18 solar farms and approved 89%, taking a median of 3.2 months. See every solar farm decision in Uttlesford →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 44 | 0.5 km |
Solar Photovoltaics · Operational | 10.8 | 1.8 km |
Solar Photovoltaics · Operational | 4.9 | 2.4 km |
Anaerobic Digestion · Operational | 1 | 3.5 km |
Solar Photovoltaics · Operational | 19 | 7.3 km |
Solar Photovoltaics · Operational | 0.17 | 8.3 km |
Solar Photovoltaics · Operational | 5.3 | 9.3 km |
Landfill Gas · Operational | 1.1 | 11.1 km |
How big is Spriggs Farm?
Spriggs Farm has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Spriggs Farm?
REPD records the operator as Abic. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Spriggs Farm approved and built?
The application was submitted on 8 November 2012. Permission was granted on 17 January 2013, 2 months later. The site became operational on 30 June 2013, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1166.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode