Renewable sites › Hyde Farm
Hyde Farm
Hyde Farm is an operational 10.8 MW solar farm in Uttlesford, generating since 13 November 2014. Planning permission was granted on 22 November 2013, 3 months after submission. Operator of record: Lightsource Renewable Energy / Push Energy.
Planning and build timeline
| Application submitted | 27 August 2013 |
| Permission granted | 22 November 2013 3 months after submission |
| Operational | 13 November 2014 12 months after consent |
Screening a site of your own?
Uttlesford approves 89% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Hyde Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Uttlesford’s record on solar
Uttlesford has decided 18 solar farms and approved 89%, taking a median of 3.2 months. See every solar farm decision in Uttlesford →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 4.9 | 1.1 km |
Solar Photovoltaics · Operational | 12 | 1.8 km |
Solar Photovoltaics · Operational | 44 | 1.9 km |
Anaerobic Digestion · Operational | 1 | 4.5 km |
Solar Photovoltaics · Operational | 0.17 | 6.5 km |
Solar Photovoltaics · Operational | 5.3 | 8.1 km |
Solar Photovoltaics · Operational | 19 | 9.1 km |
Solar Photovoltaics · Under Construction | 9.89 | 10.6 km |
How big is Hyde Farm?
Hyde Farm has a recorded installed capacity of 10.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Hyde Farm?
REPD records the operator as Lightsource Renewable Energy / Push Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Hyde Farm approved and built?
The application was submitted on 27 August 2013. Permission was granted on 22 November 2013, 3 months later. The site became operational on 13 November 2014, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1322.
Novarly Parcel · official public data, read properly · parcel.novarly.com