Renewable planning SolarUttlesford

Solar planning in Uttlesford

Uttlesford has decided 18 solar farms and approved 89% of them, taking a median of 3.2 months to decide. Consented capacity: 289 MW. 7 applications still awaiting a decision.

89%
Approved
16 granted · 2 refused
3.2 mo
Median decision
UK 2.3 mo
289 MW
Consented
58 MW refused
3
Appeals
2 allowed on appeal

How Uttlesford compares

Against the 298 UK authorities with 5+ solar decisions, Uttlesford sits in the 24th percentile for approval rate (4 points below the England average) and the 27th percentile for speed.

Decisions by year

35Approved — 3 (2013)313Approved — 1 (2014)114Refused — 1 (2015)115Approved — 1 (2016)116Approved — 1 (2020)120Approved — 3 (2022)322Approved — 3 (2023)323Approved — 3 (2024)324Approved — 1 (2025)125Refused — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (27)

SchemeMWStatusDecided
Maggots End Road, Berden - Solar Farm & Battery Storage
Low Carbon Limited · UTT/25/1224/FUL · 8 mo to decide
49.9Application Refused2026-01-15
Crumps Farm - Industrial & Commercial Units, Solar Farm
Crumps Estates Limited · ESS/16/24/UTT/OUT
Application Submitted2025-07-08
Merks Hill Farm, Braintree Road - Solar Farm
Sky UK Development Limited · UTT/25/1374/FUL
12Application Submitted2025-05-28
Hales Farm - Ground Mounted Photovoltaic Solar Panels
Hales Farms Limited · UTT/24/3069/FUL · 1.6 mo to decide
0.31Awaiting Construction2025-02-20
Wickham Hall Estate Solar Photovoltaic Farm
Endurance Energy Wickham Hall Limited · UTT/24/1417/PINS · 2.6 mo to decide
20Awaiting Construction2024-09-13
Berden Hall Solar Farm
Statera Energy · UTT/22/2046/PINS · 23.5 mo to decide
49.99Awaiting Construction2024-07-18
Dunmow Solar Farm, Chelmsford Road - Solar Farm
Dunmow Solar Limited · UTT/23/2136/FUL · 9.7 mo to decide
9.89Under Construction2024-07-04
Felsted School Road - Solar Photovoltaic Farm & Battery storage
Clearstone Energy · UTT/22/0007/FUL · 31.9 mo to decide
49.9Awaiting Construction2023-09-05
St Marys School, Hampton Road - Solar panels
Solar Optiomns For School Limited · UTT/23/1481/FUL · 1.8 mo to decide
0.18Awaiting Construction2023-08-11
St Marys School, Hampton Road - Solar Panels
Solar Options For Schools Limited · UTT/23/0715/PA14J · 1.5 mo to decide
0.17Revised2023-05-03
Long Meadow Solar Farm
Low Carbon Solar Park 4 Limited · UTT/21/0688/FUL · 26.9 mo to decide
19Operational2023-04-21
Chesterford Park - Green Energy Hub
Chesterford Park (General Partner) Limited · UTT/21/2846/FUL · 15.3 mo to decide
2.8Awaiting Construction2022-12-23
Thaxted - Solar farm
Low Carbon Limited · UTT/21/1833/FUL · 15.7 mo to decide
40Awaiting Construction2022-09-29
Stanstead Solar Project
Manchester Airport Group Plc · S62A/22/0000004 · 2.8 mo to decide
14.3Under Construction2022-08-24
Wickham Hall Estate Solar Photovoltaic Farm
Endurance Energy Wickham Hall Limited · UTT/21/3108/FUL · 4.6 mo to decide
Revised2022-04-19
Maggots End Road, Berden - Solar Farm & Battery Storage
Low Carbon Limited · UTT/21/3356/FUL · 2.4 mo to decide
49.9Revised2022-01-24
Terriers Farm
Low Carbon · UTT/19/1864/FUL · 5.3 mo to decide
44Operational2020-01-09
Land west of Hawkspur Green (Hill Hall Solar)
Lightsource Renewable Energy · UTT/15/0676/FUL · 13.3 mo to decide
4.9Operational2016-04-14
Bumpstead Hill
Lightsource Renewable Energy · UTT/15/2318/FUL · 3.2 mo to decide
5Revised2015-11-19
Butlers Farm
Push Energy · UTT/14/2755/FUL · 5.8 mo to decide
7.7Appeal Refused2015-03-16
Tooleys Farm
Lightsource Renewable Energy · UTT/14/2739/FUL · 3 mo to decide
5.3Operational2014-12-16
Tye Green Farm
Lightsource Renewable Energy · UTT/14/1916/FUL
14.9Application Withdrawn2014-09-25
Butlers Farm
Push Energy · UTT/13/2889/FUL · 3 mo to decide
9.3Revised2014-01-30
Hyde Farm
Lightsource Renewable Energy / Push Energy · UTT/13/2207/FUL · 2.9 mo to decide
10.8Operational2013-11-22
Drapers Farm Solar Park
Lightsource Renewable Energy · UTT/13/0561/FUL · 2.8 mo to decide
6Operational2013-06-07
Spriggs Farm
Abic · UTT/12/5601/FUL · 2.3 mo to decide
12Operational2013-01-17
Weston Group HQ - Solar Panels
Weston Homes
No Application Required

Does Uttlesford approve solar farms?

Yes — of the 18 solar farms Uttlesford has decided, 89% were approved (16 granted, 2 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Uttlesford?

The median time from application to decision is 3.2 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Uttlesford consented?

289 MW has been consented across 16 approved schemes, with 58 MW refused. A further 7 applications awaits a decision.

Other technologies in Uttlesford

Battery storage in UttlesfordOnshore wind in Uttlesford

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.