Novarly ParcelRenewable sites

Renewable sitesStation Works AD

Station Works AD

Station Works AD is an operational 1 MW anaerobic digestion plant in Uttlesford, generating since 1 February 2012. REPD does not record the planning grant date. Operator of record: Privilege Finance/ BioWatt.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 1 February 2012
Anaerobic Digestion
Technology
Privilege Finance/ BioWatt
Uttlesford
Authority
England

Planning and build timeline

Application submitted13 September 2010
Permission grantednot recorded
Operational1 February 2012

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Uttlesford: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Station Works AD’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
443 km
Solar Photovoltaics · Operational
123.5 km
Solar Photovoltaics · Operational
10.84.5 km
Solar Photovoltaics · Operational
4.95.5 km
Solar Photovoltaics · Operational
197.2 km
Landfill Gas · Operational
1.17.8 km
Solar Photovoltaics · Under Construction
14.38 km
Solar Photovoltaics · Operational
5.38.4 km

How big is Station Works AD?

Station Works AD has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Station Works AD?

REPD records the operator as Privilege Finance/ BioWatt. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Station Works AD approved and built?

The application was submitted on 13 September 2010. REPD does not record a grant date. The site became operational on 1 February 2012.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6538.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode