Renewable sites › Snarlton Farm (Melksham solar farm)
Snarlton Farm (Melksham solar farm)
Snarlton Farm (Melksham solar farm) is operational in Wiltshire with a recorded capacity of 49.6 MW, and has been generating since 2016-03-31.
Planning and build timeline
| Application submitted | 2013-11-19 |
| Permission granted | 2015-06-18 19 months after submission |
| Operational | 2016-03-31 9 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Wiltshire’s record on solar
Wiltshire has decided 103 solar farms and approved 93%, taking a median of 4 months. See every solar farm decision in Wiltshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
CRAYSMARSH SOLAR FARM Solar Photovoltaics · Operational | 1.8 | 1.2 km |
Bromham House Farm Anaerobic Digestion · Operational | 1.5 | 4.2 km |
Wick Farm, Melksham Substation Battery · Under Construction | — | 5 km |
Wick Farm Melksham Substation Solar Photovoltaics · Under Construction | 49.9 | 5 km |
Roundponds Farm Solar Park Solar Photovoltaics · Operational | 13.5 | 5.1 km |
Melksham Substation East Storage Battery · Operational | 50 | 5.3 km |
Norrington Common Solar Farm Solar Photovoltaics · Operational | 10 | 5.7 km |
Land north of Ashton Road Solar Photovoltaics · Operational | 4 | 7.3 km |
How big is Snarlton Farm (Melksham solar farm)?
Snarlton Farm (Melksham solar farm) has a recorded installed capacity of 49.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Snarlton Farm (Melksham solar farm)?
REPD records the operator as Foresight. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Snarlton Farm (Melksham solar farm) approved and built?
The application was submitted on 2013-11-19. Permission was granted on 2015-06-18, 19 months later. The site became operational on 2016-03-31, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1335.
Novarly Parcel · official public data, read properly · parcel.novarly.com