Renewable sitesWick Farm, Melksham Substation

Wick Farm, Melksham Substation

Wick Farm, Melksham Substation is a battery storage site under construction in Wiltshire. Planning permission was granted on 17 December 2021, 16 months after submission. Operator of record: JBM Solar Projects.

Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
JBM Solar Projects
Wiltshire
Authority
England

Planning and build timeline

Application submitted19 August 2020
Permission granted17 December 2021
16 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Wiltshire approves 97% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Wick Farm, Melksham Substation’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Wiltshire’s record on battery storage

Wiltshire has decided 30 battery storage schemes and approved 97%, taking a median of 13.9 months. See every battery storage scheme decision in Wiltshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Under Construction
49.90 km
Battery · Operational
501.3 km
Solar Photovoltaics · Operational
13.53.4 km
Solar Photovoltaics · Operational
103.4 km
Solar Photovoltaics · Operational
49.65 km
Solar Photovoltaics · Operational
6.35.6 km
Solar Photovoltaics · Operational
1.85.7 km
Anaerobic Digestion · Operational
1.57.2 km

How big is Wick Farm, Melksham Substation?

REPD does not record an installed capacity for Wick Farm, Melksham Substation.

Who operates Wick Farm, Melksham Substation?

REPD records the operator as JBM Solar Projects. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Wick Farm, Melksham Substation approved and built?

The application was submitted on 19 August 2020. Permission was granted on 17 December 2021, 16 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8063.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode