Novarly ParcelRenewable sites

Renewable sitesBromham House Farm

Bromham House Farm

Bromham House Farm is operational in Wiltshire with a recorded capacity of 1.5 MW, and has been generating since 2018-05-15.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2018-05-15
Anaerobic Digestion
Technology
A J Butler & Sons Ltd
Wiltshire
Authority
England

Planning and build timeline

Application submitted2015-05-08
Permission granted2015-09-24
5 months after submission
Operational2018-05-15
32 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Snarlton Farm (Melksham solar farm)
Solar Photovoltaics · Operational
49.64.2 km
CRAYSMARSH SOLAR FARM
Solar Photovoltaics · Operational
1.85.1 km
Hopton Road Industrial Estate
Solar Photovoltaics · Operational
1.35.4 km
Sands Farm Quarry Landfill Site
Landfill Gas · Operational
3.56.7 km
Compton Bassett Landfill
Landfill Gas · Operational
26.8 km
Wick Farm Melksham Substation
Solar Photovoltaics · Under Construction
49.97.2 km
Wick Farm, Melksham Substation
Battery · Under Construction
7.2 km
High Penn Solar Park
Solar Photovoltaics · Operational
9.67.5 km

How big is Bromham House Farm?

Bromham House Farm has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bromham House Farm?

REPD records the operator as A J Butler & Sons Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bromham House Farm approved and built?

The application was submitted on 2015-05-08. Permission was granted on 2015-09-24, 5 months later. The site became operational on 2018-05-15, 32 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5652.