Renewable sitesLand north of Ashton Road

Land north of Ashton Road

Land north of Ashton Road is an operational 4 MW solar farm in Wiltshire, generating since 24 March 2017. Planning permission was granted on 22 December 2015, 5 months after submission. Operator of record: Conergy.

4 MW
Capacity
as recorded in REPD
Operational
Status
since 24 March 2017
Solar Photovoltaics
Technology
Conergy
Wiltshire
Authority
England

Planning and build timeline

Application submitted22 July 2015
Permission granted22 December 2015
5 months after submission
Operational24 March 2017
15 months after consent

Screening a site of your own?

RedlineUK · £39

Wiltshire approves 93% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Land north of Ashton Road’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Wiltshire’s record on solar

Wiltshire has decided 103 solar farms and approved 93%, taking a median of 4 months. See every solar farm decision in Wiltshire

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
9.13.1 km
Sewage Sludge Digestion · Operational
1.24.5 km
Solar Photovoltaics · Operational
204.9 km
Solar Photovoltaics · Operational
16.65.2 km
Solar Photovoltaics · Operational
55.2 km
Solar Photovoltaics · Operational
3.55.5 km
Solar Photovoltaics · Operational
55.5 km
Landfill Gas · Operational
1.15.6 km

How big is Land north of Ashton Road?

Land north of Ashton Road has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land north of Ashton Road?

REPD records the operator as Conergy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land north of Ashton Road approved and built?

The application was submitted on 22 July 2015. Permission was granted on 22 December 2015, 5 months later. The site became operational on 24 March 2017, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5498.