Renewable sites › Skelton Grange Landfill
Skelton Grange Landfill
Skelton Grange Landfill is operational in Leeds with a recorded capacity of 5.2 MW, and has been generating since 2007-05-01.
Planning and build timeline
| Application submitted | 2004-12-16 |
| Permission granted | 2005-03-17 3 months after submission |
| Operational | 2007-05-01 25 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
- Green Belt — Leeds
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Knostrop Sewage Treatment Works Anaerobic Digestion · Operational | 4 | 3.2 km |
Skelton Grange � Energy Recovery Facility EfW Incineration · Under Construction | 49 | 3.5 km |
Knostrop WWTW AD Anaerobic Digestion · Operational | 2.4 | 4.2 km |
Cross Green ERF EfW Incineration · Operational | 11.6 | 4.3 km |
LVF Packaging - Solar Panel Solar Photovoltaics · Operational | 0.3 | 5.4 km |
Barnsdale Road Solar Park Solar Photovoltaics · Under Construction | 40 | 5.6 km |
TF and JH Braime Holdings Factory Solar Photovoltaics · Operational | 0.2 | 6 km |
Regent Street, Sheepscar - Solar Panels Solar Photovoltaics · Operational | 0.22 | 6.8 km |
How big is Skelton Grange Landfill?
Skelton Grange Landfill has a recorded installed capacity of 5.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Skelton Grange Landfill?
REPD records the operator as Biffa. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Skelton Grange Landfill approved and built?
The application was submitted on 2004-12-16. Permission was granted on 2005-03-17, 3 months later. The site became operational on 2007-05-01, 25 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 680.