Renewable sites › Knostrop Sewage Treatment Works
Knostrop Sewage Treatment Works
Knostrop Sewage Treatment Works is operational in Leeds with a recorded capacity of 4 MW, and has been generating since 2018-12-03.
Planning and build timeline
| Application submitted | 2016-05-02 |
| Permission granted | 2016-09-06 4 months after submission |
| Operational | 2018-12-03 27 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Skelton Grange � Energy Recovery Facility EfW Incineration · Under Construction | 49 | 0.7 km |
Knostrop WWTW AD Anaerobic Digestion · Operational | 2.4 | 1.1 km |
Cross Green ERF EfW Incineration · Operational | 11.6 | 1.1 km |
LVF Packaging - Solar Panel Solar Photovoltaics · Operational | 0.3 | 2.3 km |
TF and JH Braime Holdings Factory Solar Photovoltaics · Operational | 0.2 | 2.9 km |
Skelton Grange Landfill Landfill Gas · Operational | 5.2 | 3.2 km |
Regent Street, Sheepscar - Solar Panels Solar Photovoltaics · Operational | 0.22 | 3.7 km |
Buslingthorpe Power Station (Leeds North) Biomass (dedicated) · Operational | 2 | 5 km |
How big is Knostrop Sewage Treatment Works?
Knostrop Sewage Treatment Works has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Knostrop Sewage Treatment Works?
REPD records the operator as Yorkshire Water. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Knostrop Sewage Treatment Works approved and built?
The application was submitted on 2016-05-02. Permission was granted on 2016-09-06, 4 months later. The site became operational on 2018-12-03, 27 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6123.
Novarly Parcel · official public data, read properly · parcel.novarly.com