Renewable sites › Cross Green ERF
Cross Green ERF
Cross Green ERF is an operational 11.6 MW energy-from-waste plant in Leeds, generating since 20 April 2016. Planning permission was granted on 8 February 2013, 7 months after submission. Operator of record: Veolia.
Planning and build timeline
| Application submitted | 27 June 2012 |
| Permission granted | 8 February 2013 7 months after submission |
| Operational | 20 April 2016 38 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Leeds: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Cross Green ERF’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Anaerobic Digestion · Operational | 2.4 | 1 km |
Anaerobic Digestion · Operational | 4 | 1.1 km |
EfW Incineration · Under Construction | 49 | 1.4 km |
Solar Photovoltaics · Operational | 0.3 | 1.6 km |
Solar Photovoltaics · Operational | 0.2 | 1.9 km |
Solar Photovoltaics · Operational | 0.22 | 2.6 km |
Biomass (dedicated) · Operational | 2 | 3.9 km |
Landfill Gas · Operational | 5.2 | 4.3 km |
How big is Cross Green ERF?
Cross Green ERF has a recorded installed capacity of 11.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Cross Green ERF?
REPD records the operator as Veolia. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Cross Green ERF approved and built?
The application was submitted on 27 June 2012. Permission was granted on 8 February 2013, 7 months later. The site became operational on 20 April 2016, 38 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 935.
Novarly Parcel · official public data, read properly · parcel.novarly.com