Renewable sites › Skelton Grange � Energy Recovery Facility
Skelton Grange � Energy Recovery Facility
Skelton Grange � Energy Recovery Facility is under construction in Leeds with a recorded capacity of 49 MW.
Planning and build timeline
| Application submitted | 2011-09-27 |
| Permission granted | 2023-05-25 140 months after submission |
| Operational | not recorded |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Knostrop Sewage Treatment Works Anaerobic Digestion · Operational | 4 | 0.7 km |
Knostrop WWTW AD Anaerobic Digestion · Operational | 2.4 | 0.7 km |
Cross Green ERF EfW Incineration · Operational | 11.6 | 1.4 km |
LVF Packaging - Solar Panel Solar Photovoltaics · Operational | 0.3 | 2 km |
TF and JH Braime Holdings Factory Solar Photovoltaics · Operational | 0.2 | 2.7 km |
Skelton Grange Landfill Landfill Gas · Operational | 5.2 | 3.5 km |
Regent Street, Sheepscar - Solar Panels Solar Photovoltaics · Operational | 0.22 | 3.8 km |
Buslingthorpe Power Station (Leeds North) Biomass (dedicated) · Operational | 2 | 5.2 km |
How big is Skelton Grange � Energy Recovery Facility?
Skelton Grange � Energy Recovery Facility has a recorded installed capacity of 49 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Skelton Grange � Energy Recovery Facility?
REPD records the operator as Scottish & Southern Energy Scottish Hydro Electric. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Skelton Grange � Energy Recovery Facility approved and built?
The application was submitted on 2011-09-27. Permission was granted on 2023-05-25, 140 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 10448.