Regent Street, Sheepscar - Solar Panels is operational in Leeds with a recorded capacity of 0.22 MW, and has been generating since 2023-06-01.

0.22 MW
Capacity
as recorded in REPD
Operational
Status
since 2023-06-01
Solar Photovoltaics
Technology
Stokers Limited
Leeds
Authority
England

Planning and build timeline

Application submitted2022-08-19
Permission granted2023-05-18
9 months after submission
Operational2023-06-01
0 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Leeds’s record on solar

Leeds has decided 55 solar farms and approved 98%, taking a median of 1.6 months. See every solar farm decision in Leeds

Other built sites within 15 km

SiteMWDistance
Buslingthorpe Power Station (Leeds North)
Biomass (dedicated) · Operational
21.4 km
TF and JH Braime Holdings Factory
Solar Photovoltaics · Operational
0.21.7 km
LVF Packaging - Solar Panel
Solar Photovoltaics · Operational
0.32.3 km
Cross Green ERF
EfW Incineration · Operational
11.62.6 km
Knostrop WWTW AD
Anaerobic Digestion · Operational
2.43.1 km
Knostrop Sewage Treatment Works
Anaerobic Digestion · Operational
43.7 km
Skelton Grange � Energy Recovery Facility
EfW Incineration · Under Construction
493.8 km
Skelton Grange Landfill
Landfill Gas · Operational
5.26.8 km

How big is Regent Street, Sheepscar - Solar Panels?

Regent Street, Sheepscar - Solar Panels has a recorded installed capacity of 0.22 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Regent Street, Sheepscar - Solar Panels?

REPD records the operator as Stokers Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Regent Street, Sheepscar - Solar Panels approved and built?

The application was submitted on 2022-08-19. Permission was granted on 2023-05-18, 9 months later. The site became operational on 2023-06-01, 0 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 12054.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council