Buslingthorpe Power Station (Leeds North)

Buslingthorpe Power Station (Leeds North) is an operational 2 MW biomass plant in Leeds, generating since 14 October 2011. Planning permission was granted on 30 December 2010, 3 months after submission. Operator of record: Living Power (REG Bio-Power).

2 MW
Capacity
as recorded in REPD
Operational
Status
since 14 October 2011
Biomass (dedicated)
Technology
Living Power (REG Bio-Power)
Leeds
Authority
England

Planning and build timeline

Application submitted30 September 2010
Permission granted30 December 2010
3 months after submission
Operational14 October 2011
9 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Leeds: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Buslingthorpe Power Station (Leeds North)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
0.221.4 km
Solar Photovoltaics · Operational
0.23 km
Solar Photovoltaics · Operational
0.33.6 km
EfW Incineration · Operational
11.63.9 km
Anaerobic Digestion · Operational
2.44.5 km
Anaerobic Digestion · Operational
45 km
EfW Incineration · Under Construction
495.2 km
Landfill Gas · Operational
5.28 km

How big is Buslingthorpe Power Station (Leeds North)?

Buslingthorpe Power Station (Leeds North) has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Buslingthorpe Power Station (Leeds North)?

REPD records the operator as Living Power (REG Bio-Power). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Buslingthorpe Power Station (Leeds North) approved and built?

The application was submitted on 30 September 2010. Permission was granted on 30 December 2010, 3 months later. The site became operational on 14 October 2011, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 26.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode