Renewable sites › Royal Seaforth Dock Wind Farm
Royal Seaforth Dock Wind Farm
Royal Seaforth Dock Wind Farm is an operational 3 MW onshore wind farm in Sefton, generating since 24 April 1999. Planning permission was granted on 22 August 1997, 22 months after submission. Operator of record: Mersey Docks and Harbour Company and Windcluster Limited.
Planning and build timeline
| Application submitted | 12 October 1995 |
| Permission granted | 22 August 1997 22 months after submission |
| Operational | 24 April 1999 20 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Sefton: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Royal Seaforth Dock Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 10 | 2.9 km |
Battery · Under Construction | 20 | 3.6 km |
Battery · Operational | 2 | 6 km |
Landfill Gas · Operational | 2.3 | 6.6 km |
Solar Photovoltaics · Under Construction | 0.63 | 8.5 km |
Battery · Operational | 20 | 9 km |
Battery · Operational | 49.9 | 9 km |
Battery · Operational | 49.9 | 9 km |
How big is Royal Seaforth Dock Wind Farm?
Royal Seaforth Dock Wind Farm has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Royal Seaforth Dock Wind Farm?
REPD records the operator as Mersey Docks and Harbour Company and Windcluster Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Royal Seaforth Dock Wind Farm approved and built?
The application was submitted on 12 October 1995. Permission was granted on 22 August 1997, 22 months later. The site became operational on 24 April 1999, 20 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2574.