Renewable sites › Royal Seaforth Dock Wind Farm
Royal Seaforth Dock Wind Farm
Royal Seaforth Dock Wind Farm is operational in Sefton with a recorded capacity of 3 MW, and has been generating since 1999-04-24.
Planning and build timeline
| Application submitted | 1995-10-12 |
| Permission granted | 1997-08-22 22 months after submission |
| Operational | 1999-04-24 20 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Port of Liverpool - wind Wind Onshore · Operational | 10 | 2.9 km |
Hawthorne Road Battery · Under Construction | 20 | 3.6 km |
Burbo Bank Energy Storage Battery · Operational | 2 | 6 km |
Bidston Moss Landfill Scheme Landfill Gas · Operational | 2.3 | 6.6 km |
Deyes Academy Redevelopment Solar Photovoltaics · Under Construction | 0.63 | 8.5 km |
Land at Carnegie Road Battery · Operational | 20 | 9 km |
Lister Drive Battery · Operational | 49.9 | 9 km |
Liverpool Energy Management Facility Battery · Operational | 49.9 | 9 km |
How big is Royal Seaforth Dock Wind Farm?
Royal Seaforth Dock Wind Farm has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Royal Seaforth Dock Wind Farm?
REPD records the operator as Mersey Docks and Harbour Company and Windcluster Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Royal Seaforth Dock Wind Farm approved and built?
The application was submitted on 1995-10-12. Permission was granted on 1997-08-22, 22 months later. The site became operational on 1999-04-24, 20 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2574.
Novarly Parcel · official public data, read properly · parcel.novarly.com