Novarly ParcelRenewable sites

Renewable sitesBurbo Bank Energy Storage

Burbo Bank Energy Storage

Burbo Bank Energy Storage is an operational 2 MW battery storage site in Wirral, generating since 24 December 2018. REPD does not record the planning grant date. Operator of record: �rsted.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 24 December 2018
Battery
Technology
�rsted
Wirral
Authority
England

Planning and build timeline

Application submitted14 April 2017
Permission grantednot recorded
Operational24 December 2018

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Wirral: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Burbo Bank Energy Storage’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
2.31.4 km
Wind Onshore · Operational
105.3 km
Wind Onshore · Operational
36 km
Battery · Under Construction
206.9 km
Landfill Gas · Operational
38 km
Battery · Operational
208.5 km
Battery · Operational
49.98.5 km
Battery · Operational
49.98.5 km

How big is Burbo Bank Energy Storage?

Burbo Bank Energy Storage has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Burbo Bank Energy Storage?

REPD records the operator as �rsted. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Burbo Bank Energy Storage approved and built?

The application was submitted on 14 April 2017. REPD does not record a grant date. The site became operational on 24 December 2018.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6992.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode