Renewable sitesDeyes Academy Redevelopment

Deyes Academy Redevelopment

Deyes Academy Redevelopment is a 0.63 MW solar farm under construction in Sefton. Planning permission was granted on 8 June 2022, 3 months after submission. Operator of record: Deyes High School (Lydiate Learning Trust).

0.63 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Solar Photovoltaics
Technology
Deyes High School (Lydiate Learning Trust)
Sefton
Authority
England

Planning and build timeline

Application submitted7 March 2022
Permission granted8 June 2022
3 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Sefton approves 97% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Deyes Academy Redevelopment’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Sefton’s record on solar

Sefton has decided 30 solar farms and approved 97%, taking a median of 1.6 months. See every solar farm decision in Sefton

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
206.7 km
Solar Photovoltaics · Operational
0.86.8 km
Wind Onshore · Operational
108.3 km
Wind Onshore · Operational
38.5 km
Solar Photovoltaics · Under Construction
58.7 km
Solar Photovoltaics · Under Construction
58.8 km
Solar Photovoltaics · Operational
2.59.9 km
Battery · Operational
29.9 km

How big is Deyes Academy Redevelopment?

Deyes Academy Redevelopment has a recorded installed capacity of 0.63 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Deyes Academy Redevelopment?

REPD records the operator as Deyes High School (Lydiate Learning Trust). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Deyes Academy Redevelopment approved and built?

The application was submitted on 7 March 2022. Permission was granted on 8 June 2022, 3 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11815.