Novarly ParcelRenewable sites

Renewable sitesBidston Moss Landfill Scheme

Bidston Moss Landfill Scheme

Bidston Moss Landfill Scheme is operational in Wirral with a recorded capacity of 2.3 MW, and has been generating since 1998-01-19.

2.3 MW
Capacity
as recorded in REPD
Operational
Status
since 1998-01-19
Landfill Gas
Technology
Bidston Methane Ltd
Wirral
Authority
England

Planning and build timeline

Application submitted1997-11-03
Permission granted1997-12-15
1 months after submission
Operational1998-01-19
1 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Burbo Bank Energy Storage
Battery · Operational
21.4 km
Port of Liverpool - wind
Wind Onshore · Operational
106.4 km
Royal Seaforth Dock Wind Farm
Wind Onshore · Operational
36.6 km
Hawthorne Road
Battery · Under Construction
208.1 km
Bromborough Dock Landfill Scheme
Landfill Gas · Operational
38.8 km
Bromborough Dock
Landfill Gas · Operational
3.79.4 km
Land at Carnegie Road
Battery · Operational
209.9 km
Lister Drive
Battery · Operational
49.99.9 km

How big is Bidston Moss Landfill Scheme?

Bidston Moss Landfill Scheme has a recorded installed capacity of 2.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Bidston Moss Landfill Scheme?

REPD records the operator as Bidston Methane Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Bidston Moss Landfill Scheme approved and built?

The application was submitted on 1997-11-03. Permission was granted on 1997-12-15, 1 months later. The site became operational on 1998-01-19, 1 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 551.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council