Renewable sites › Port of Liverpool - wind
Port of Liverpool - wind
Port of Liverpool - wind is an operational 10 MW onshore wind farm in Sefton, generating since 1 February 2009. Planning permission was granted on 8 December 2005, 4 months after submission. Operator of record: Mersey Docks and Harbour Company.
Planning and build timeline
| Application submitted | 17 August 2005 |
| Permission granted | 8 December 2005 4 months after submission |
| Operational | 1 February 2009 38 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Sefton: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Port of Liverpool - wind’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Under Construction | 20 | 1.6 km |
Wind Onshore · Operational | 3 | 2.9 km |
Battery · Operational | 2 | 5.3 km |
Battery · Operational | 20 | 6.1 km |
Battery · Operational | 49.9 | 6.1 km |
Battery · Operational | 49.9 | 6.1 km |
Landfill Gas · Operational | 2.3 | 6.4 km |
Solar Photovoltaics · Under Construction | 0.63 | 8.3 km |
How big is Port of Liverpool - wind?
Port of Liverpool - wind has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Port of Liverpool - wind?
REPD records the operator as Mersey Docks and Harbour Company. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Port of Liverpool - wind approved and built?
The application was submitted on 17 August 2005. Permission was granted on 8 December 2005, 4 months later. The site became operational on 1 February 2009, 38 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3533.