Renewable sites › Port of Liverpool - wind
Port of Liverpool - wind
Port of Liverpool - wind is operational in Sefton with a recorded capacity of 10 MW, and has been generating since 2009-02-01.
Planning and build timeline
| Application submitted | 2005-08-17 |
| Permission granted | 2005-12-08 4 months after submission |
| Operational | 2009-02-01 38 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Hawthorne Road Battery · Under Construction | 20 | 1.6 km |
Royal Seaforth Dock Wind Farm Wind Onshore · Operational | 3 | 2.9 km |
Burbo Bank Energy Storage Battery · Operational | 2 | 5.3 km |
Land at Carnegie Road Battery · Operational | 20 | 6.1 km |
Liverpool Energy Management Facility Battery · Operational | 49.9 | 6.1 km |
Lister Drive Battery · Operational | 49.9 | 6.1 km |
Bidston Moss Landfill Scheme Landfill Gas · Operational | 2.3 | 6.4 km |
Deyes Academy Redevelopment Solar Photovoltaics · Under Construction | 0.63 | 8.3 km |
How big is Port of Liverpool - wind?
Port of Liverpool - wind has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Port of Liverpool - wind?
REPD records the operator as Mersey Docks and Harbour Company. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Port of Liverpool - wind approved and built?
The application was submitted on 2005-08-17. Permission was granted on 2005-12-08, 4 months later. The site became operational on 2009-02-01, 38 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3533.