Renewable sites › Rhyd-y-Pandy Solar Farm
Rhyd-y-Pandy Solar Farm
Rhyd-y-Pandy Solar Farm is operational in Swansea with a recorded capacity of 6 MW, and has been generating since 2015-03-06.
Planning and build timeline
| Application submitted | 2013-11-15 |
| Permission granted | 2014-02-20 3 months after submission |
| Operational | 2015-03-06 12 months after consent |
Swansea’s record on solar
Swansea has decided 16 solar farms and approved 88%, taking a median of 4.5 months. See every solar farm decision in Swansea →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Abergelli Glas Solar Farm Solar Photovoltaics · Operational | 7.7 | 0.7 km |
Swansea Greener Grid Park Battery · Under Construction | — | 0.8 km |
Brynwhilach Solar Park Solar Photovoltaics · Operational | 4 | 1.7 km |
Gelliwern Isaf Farm Solar Photovoltaics · Operational | 6 | 3.7 km |
Mynydd Y Gwair Wind Farm Wind Onshore · Operational | 32.8 | 5.9 km |
PwllfaWatkin Landfill Gas Site Landfill Gas · Operational | 3.2 | 7 km |
Carn Nicholas Farm Solar Photovoltaics · Under Construction | 5 | 7.5 km |
Carn Nicholas Farm (Extension) Solar Photovoltaics · Operational | 10 | 7.5 km |
How big is Rhyd-y-Pandy Solar Farm?
Rhyd-y-Pandy Solar Farm has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Rhyd-y-Pandy Solar Farm?
REPD records the operator as Wessex Solar Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Rhyd-y-Pandy Solar Farm approved and built?
The application was submitted on 2013-11-15. Permission was granted on 2014-02-20, 3 months later. The site became operational on 2015-03-06, 12 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2354.