Renewable sites › Gelliwern Isaf Farm
Gelliwern Isaf Farm
Gelliwern Isaf Farm is an operational 6 MW solar farm in Swansea, generating since 31 March 2015. Planning permission was granted on 12 November 2014, 6 months after submission. Operator of record: Solar Park Developments.
Planning and build timeline
| Application submitted | 21 May 2014 |
| Permission granted | 12 November 2014 6 months after submission |
| Operational | 31 March 2015 5 months after consent |
Screening a site of your own?
Swansea approves 88% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Gelliwern Isaf Farm’s recorded coordinate — swap in your own postcode or coordinates.
Swansea’s record on solar
Swansea has decided 16 solar farms and approved 88%, taking a median of 4.5 months. See every solar farm decision in Swansea →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 4 | 2.8 km |
Battery · Under Construction | — | 3 km |
Solar Photovoltaics · Operational | 7.7 | 3.1 km |
Solar Photovoltaics · Operational | 6 | 3.7 km |
Wind Onshore · Operational | 32.8 | 6.7 km |
Solar Photovoltaics · Operational | 4 | 7.1 km |
Solar Photovoltaics · Operational | 1.4 | 7.6 km |
Solar Photovoltaics · Operational | 13.5 | 8.5 km |
How big is Gelliwern Isaf Farm?
Gelliwern Isaf Farm has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Gelliwern Isaf Farm?
REPD records the operator as Solar Park Developments. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Gelliwern Isaf Farm approved and built?
The application was submitted on 21 May 2014. Permission was granted on 12 November 2014, 6 months later. The site became operational on 31 March 2015, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2334.