Novarly ParcelRenewable sites

Renewable sitesAbergelli Glas Solar Farm

Abergelli Glas Solar Farm

Abergelli Glas Solar Farm is an operational 7.7 MW solar farm in Swansea, generating since 15 March 2015. Planning permission was granted on 28 May 2013, 3 months after submission. Operator of record: Foresight.

7.7 MW
Capacity
as recorded in REPD
Operational
Status
since 15 March 2015
Solar Photovoltaics
Technology
Foresight
Swansea
Authority
Wales

Planning and build timeline

Application submitted18 February 2013
Permission granted28 May 2013
3 months after submission
Operational15 March 2015
22 months after consent

Screening a site of your own?

RedlineUK · £39

Swansea approves 88% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Abergelli Glas Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Swansea’s record on solar

Swansea has decided 16 solar farms and approved 88%, taking a median of 4.5 months. See every solar farm decision in Swansea

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
60.7 km
Battery · Under Construction
0.9 km
Solar Photovoltaics · Operational
41.7 km
Solar Photovoltaics · Operational
63.1 km
Wind Onshore · Operational
32.85.4 km
Landfill Gas · Operational
3.27.2 km
Solar Photovoltaics · Under Construction
58.1 km
Solar Photovoltaics · Operational
108.1 km

How big is Abergelli Glas Solar Farm?

Abergelli Glas Solar Farm has a recorded installed capacity of 7.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Abergelli Glas Solar Farm?

REPD records the operator as Foresight. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Abergelli Glas Solar Farm approved and built?

The application was submitted on 18 February 2013. Permission was granted on 28 May 2013, 3 months later. The site became operational on 15 March 2015, 22 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1953.