Mynydd Y Gwair Wind Farm

Mynydd Y Gwair Wind Farm is an operational 32.8 MW onshore wind farm in Swansea, generating since 24 April 2019. Planning permission was granted on 8 February 2013, 5 months after submission. Operator of record: RWE Npower Renewables/ Innogy.

32.8 MW
Capacity
as recorded in REPD
Operational
Status
since 24 April 2019
Wind Onshore
Technology
RWE Npower Renewables/ Innogy
Swansea
Authority
Wales

Planning and build timeline

Application submitted11 September 2012
Permission granted8 February 2013
5 months after submission
Operational24 April 2019
74 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Swansea: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Mynydd Y Gwair Wind Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
34.52.7 km
Solar Photovoltaics · Operational
95 km
Solar Photovoltaics · Operational
7.75.4 km
Landfill Gas · Operational
3.25.6 km
Solar Photovoltaics · Operational
65.9 km
Battery · Under Construction
6.3 km
Solar Photovoltaics · Operational
66.7 km
Wind Onshore · Operational
4.77.1 km

How big is Mynydd Y Gwair Wind Farm?

Mynydd Y Gwair Wind Farm has a recorded installed capacity of 32.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Mynydd Y Gwair Wind Farm?

REPD records the operator as RWE Npower Renewables/ Innogy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Mynydd Y Gwair Wind Farm approved and built?

The application was submitted on 11 September 2012. Permission was granted on 8 February 2013, 5 months later. The site became operational on 24 April 2019, 74 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4648.