Renewable sites › PwllfaWatkin Landfill Gas Site
PwllfaWatkin Landfill Gas Site
PwllfaWatkin Landfill Gas Site is an operational 3.2 MW landfill gas site in Neath Port Talbot, generating since 1 November 2005. Planning permission was granted on 11 August 2005, 6 months after submission. Operator of record: Waste Recycling Group.
Planning and build timeline
| Application submitted | 26 January 2005 |
| Permission granted | 11 August 2005 6 months after submission |
| Operational | 1 November 2005 3 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Neath Port Talbot: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with PwllfaWatkin Landfill Gas Site’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 4.7 | 4.9 km |
Wind Onshore · Operational | 32.8 | 5.6 km |
Wind Onshore · Operational | 34.5 | 6.3 km |
Solar Photovoltaics · Operational | 6 | 7 km |
Solar Photovoltaics · Operational | 7.7 | 7.2 km |
Battery · Under Construction | — | 7.8 km |
Solar Photovoltaics · Operational | 4 | 8.7 km |
Solar Photovoltaics · Operational | 9 | 8.7 km |
How big is PwllfaWatkin Landfill Gas Site?
PwllfaWatkin Landfill Gas Site has a recorded installed capacity of 3.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates PwllfaWatkin Landfill Gas Site?
REPD records the operator as Waste Recycling Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was PwllfaWatkin Landfill Gas Site approved and built?
The application was submitted on 26 January 2005. Permission was granted on 11 August 2005, 6 months later. The site became operational on 1 November 2005, 3 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 802.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode