Solar planning in Swansea

Swansea has decided 16 solar farms and approved 88% of them, taking a median of 4.5 months to decide. Consented capacity: 70 MW. 2 applications still awaiting a decision.

88%
Approved
14 granted · 2 refused
4.5 mo
Median decision
UK 2.3 mo
70 MW
Consented
5 MW refused
4
Appeals
1 allowed on appeal

How Swansea compares

Against the 298 UK authorities with 5+ solar decisions, Swansea sits in the 21st percentile for approval rate (5 points below the England average) and the 11th percentile for speed.

Decisions by year

35Approved — 1 (2013)113Approved — 3 (2014)Refused — 1 (2014)414Approved — 3 (2015)Refused — 1 (2015)415Approved — 1 (2016)116Approved — 1 (2019)119Approved — 1 (2021)121Approved — 1 (2022)122Approved — 1 (2023)123Approved — 1 (2025)125Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (20)

SchemeMWStatusDecided
Tesco Superstore, Tidal Reach - Solar PV Array
Tesco Plc · 2025/2575/PLD · 1.1 mo to decide
0.25Awaiting Construction2026-01-06
Coed Bach Park, Gwynfryn Road - Solar Panels
Stellar Energy · 2025/1812/FUL
15Application Submitted2025-08-29
Gwenlais Farm, Carmel Road - Gwenlais Solar Farm
Solar Securities Group Limited · DNS CAS-02282-Z9M8L7 · 14.9 mo to decide
16.26Awaiting Construction2025-06-11
Tir John Solar Farm
Swansea City and County Council · 2022/1907/FUL · 8.3 mo to decide
3Awaiting Construction2023-06-13
Brunel Way, Pentrechwyth - Solar Panels
WM Morrisons Supermarkets Plc · 2022/0087/FUL · 1.8 mo to decide
0.74Awaiting Construction2022-03-31
Carn Nicholas Farm (Extension)
Innova Renewables Limited · 2020/0173/FUL · 13.5 mo to decide
10Operational2021-03-17
Eurofoods Building
Eurofoods Group · 2019/0331/FUL · 1.8 mo to decide
0.6Awaiting Construction2019-04-09
Land at Lltty Morphil Farm
Kronos Solar · 2015/1529 · 9.6 mo to decide
5Abandoned2016-05-10
Castell Ddu Solar Farm
Caledon Partners (Solar Power Parks) · 2015/1786 · 4.2 mo to decide
5Planning Permission Expired2016-01-14
Carn Nicholas Farm
Suncredit UK · 2015/1546 · 4.1 mo to decide
5Under Construction2015-12-14
Killan Farm Solar Array Extens
Y Felin Ddwr Charitable Trust · 2015/1209 · 4.9 mo to decide
1Operational2015-12-14
Cockett Valley
Renewable Developments Wales · 2014/1837 · 8.4 mo to decide
4Operational2015-08-18
Carn Nicholas Farm
Suncredit UK · 2015/1646
5Application Withdrawn2015-08-11
Gwenlais Uchaf Farm
Renewable Developments · 2014/1620 · 6.5 mo to decide
4Revised2015-05-15
Pencefnarda Uchaf Farm
Pencefnarda Solar · 2014/0761 · 8.2 mo to decide
3.6Appeal Refused2015-02-09
Gelliwern Isaf Farm
Solar Park Developments · 2014/0739 · 5.7 mo to decide
6Operational2014-11-12
Brynwhilach Solar Park
Core Pisces / Gower Power Co-op CIC · 2014/1022 · 3.6 mo to decide
4Operational2014-11-04
Webbsfield
Gower Power Community Cooperative · 2014/0876 · 2.5 mo to decide
1Appeal Refused2014-09-02
Rhyd-y-Pandy Solar Farm
Wessex Solar Energy · 2013/1639 · 3.2 mo to decide
6Operational2014-02-20
Abergelli Glas Solar Farm
Foresight · 2013/0135 · 3.3 mo to decide
7.7Operational2013-05-28

Does Swansea approve solar farms?

Yes — of the 16 solar farms Swansea has decided, 88% were approved (14 granted, 2 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Swansea?

The median time from application to decision is 4.5 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Swansea consented?

70 MW has been consented across 14 approved schemes, with 5 MW refused. A further 2 applications awaits a decision.

Other technologies in Swansea

Battery storage in SwanseaOnshore wind in Swansea

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.