Renewable sites › Regent Street - Solar Photovoltaic Panels
Regent Street - Solar Photovoltaic Panels
Regent Street - Solar Photovoltaic Panels is operational in Gateshead, and has been generating since 2022-01-01.
Planning and build timeline
| Application submitted | 2021-06-07 |
| Permission granted | 2021-09-17 3 months after submission |
| Operational | 2022-01-01 3 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Gateshead’s record on solar
Gateshead has decided 20 solar farms and approved 100%, taking a median of 1.8 months. See every solar farm decision in Gateshead →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Metrocentre Green Car Park, St Michaels Way - Photovoltaic Equipment Solar Photovoltaics · Under Construction | — | 4.2 km |
Excelsior Academy, Denton Road - Solar Panels Solar Photovoltaics · Under Construction | 0.53 | 5.9 km |
Kibblesworth Landfill Site Landfill Gas · Operational | 2.3 | 6.3 km |
PG4 St Bedes Power Generation (Extension) Landfill Gas · Operational | 2 | 7.7 km |
PG4 St Bedes Power Generation Landfill Gas · Operational | 2 | 7.7 km |
PG4 St Bedes Power Generation (Extension 2) Landfill Gas · Operational | 1 | 7.7 km |
Path Head Landfill Gas · Operational | 1 | 8 km |
Unipres building Solar Photovoltaics · Operational | 4.9 | 8.9 km |
How big is Regent Street - Solar Photovoltaic Panels?
REPD does not record an installed capacity for Regent Street - Solar Photovoltaic Panels.
Who operates Regent Street - Solar Photovoltaic Panels?
REPD records the operator as Gateshead Metropolitan Borough Council. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Regent Street - Solar Photovoltaic Panels approved and built?
The application was submitted on 2021-06-07. Permission was granted on 2021-09-17, 3 months later. The site became operational on 2022-01-01, 3 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 10255.
Novarly Parcel · official public data, read properly · parcel.novarly.com