Renewable sitesPath Head

Path Head

Path Head is operational in Gateshead with a recorded capacity of 1 MW, and has been generating since 2009-02-15.

1 MW
Capacity
as recorded in REPD
Operational
Status
since 2009-02-15
Landfill Gas
Technology
SITA UK
Gateshead
Authority
England

Planning and build timeline

Application submitted2002-01-01
Permission granted2005-03-04
38 months after submission
Operational2009-02-15
47 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Burnhills Landfill (L5)
Landfill Gas · Operational
3.82.1 km
Burnhills Landfill Scheme (L4)
Landfill Gas · Operational
1.52.1 km
Excelsior Academy, Denton Road - Solar Panels
Solar Photovoltaics · Under Construction
0.532.6 km
Metrocentre Green Car Park, St Michaels Way - Photovoltaic Equipment
Solar Photovoltaics · Under Construction
4 km
Regent Street - Solar Photovoltaic Panels
Solar Photovoltaics · Operational
8 km
Newcastle International Airport Phase 1 -Solar Farm
Solar Photovoltaics · Under Construction
38.3 km
Kibblesworth Landfill Site
Landfill Gas · Operational
2.310.6 km
Brenkley Landfill
Landfill Gas · Operational
1.912.1 km

How big is Path Head?

Path Head has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Path Head?

REPD records the operator as SITA UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Path Head approved and built?

The application was submitted on 2002-01-01. Permission was granted on 2005-03-04, 38 months later. The site became operational on 2009-02-15, 47 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 674.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council