Novarly ParcelRenewable sites

Renewable sitesPG4 St Bedes Power Generation

PG4 St Bedes Power Generation

PG4 St Bedes Power Generation is operational in County Durham with a recorded capacity of 2 MW, and has been generating since 2001-03-30.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 2001-03-30
Landfill Gas
Technology
DURHAM COUNTY WASTE MANAGEMENT LTD
County Durham
Authority
England

Planning and build timeline

Application submitted1999-12-08
Permission granted2000-06-09
6 months after submission
Operational2001-03-30
10 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
PG4 St Bedes Power Generation (Extension 2)
Landfill Gas · Operational
10.1 km
PG4 St Bedes Power Generation (Extension)
Landfill Gas · Operational
20.1 km
Kibblesworth Landfill Site
Landfill Gas · Operational
2.31.7 km
Lumley Water Treatment Works - Solar Panels
Solar Photovoltaics · Operational
1.96.5 km
Unipres building
Solar Photovoltaics · Operational
4.97.2 km
Nissan Motors Plant Extn
Wind Onshore · Operational
27.3 km
Nissan Wind Farm
Wind Onshore · Operational
47.3 km
Sedgeletch Sewage Treatment Works
Solar Photovoltaics · Under Construction
7.3 km

How big is PG4 St Bedes Power Generation?

PG4 St Bedes Power Generation has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates PG4 St Bedes Power Generation?

REPD records the operator as DURHAM COUNTY WASTE MANAGEMENT LTD. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was PG4 St Bedes Power Generation approved and built?

The application was submitted on 1999-12-08. Permission was granted on 2000-06-09, 6 months later. The site became operational on 2001-03-30, 10 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 566.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council