Renewable sites › PG4 St Bedes Power Generation (Extension)
PG4 St Bedes Power Generation (Extension)
PG4 St Bedes Power Generation (Extension) is an operational 2 MW landfill gas site in County Durham, generating since 18 July 2002. Planning permission was granted on 21 February 2002, 4 months after submission. Operator of record: DURHAM COUNTY WASTE MANAGEMENT LTD.
Planning and build timeline
| Application submitted | 26 October 2001 |
| Permission granted | 21 February 2002 4 months after submission |
| Operational | 18 July 2002 5 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in County Durham: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with PG4 St Bedes Power Generation (Extension)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
- Green Belt — County Durham
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Landfill Gas · Operational | 2 | 0.1 km |
Landfill Gas · Operational | 1 | 0.2 km |
Landfill Gas · Operational | 2.3 | 1.6 km |
Solar Photovoltaics · Operational | 1.9 | 6.5 km |
Solar Photovoltaics · Operational | 4.9 | 7.3 km |
Wind Onshore · Operational | 2 | 7.4 km |
Wind Onshore · Operational | 4 | 7.4 km |
Solar Photovoltaics · Under Construction | — | 7.4 km |
How big is PG4 St Bedes Power Generation (Extension)?
PG4 St Bedes Power Generation (Extension) has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates PG4 St Bedes Power Generation (Extension)?
REPD records the operator as DURHAM COUNTY WASTE MANAGEMENT LTD. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was PG4 St Bedes Power Generation (Extension) approved and built?
The application was submitted on 26 October 2001. Permission was granted on 21 February 2002, 4 months later. The site became operational on 18 July 2002, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 660.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode