Renewable sites › Kibblesworth Landfill Site
Kibblesworth Landfill Site
Kibblesworth Landfill Site is operational in Gateshead with a recorded capacity of 2.3 MW, and has been generating since 1998-10-26.
Planning and build timeline
| Application submitted | 1996-12-24 |
| Permission granted | 1998-06-05 17 months after submission |
| Operational | 1998-10-26 5 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — Gateshead
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
PG4 St Bedes Power Generation (Extension) Landfill Gas · Operational | 2 | 1.6 km |
PG4 St Bedes Power Generation Landfill Gas · Operational | 2 | 1.7 km |
PG4 St Bedes Power Generation (Extension 2) Landfill Gas · Operational | 1 | 1.8 km |
Regent Street - Solar Photovoltaic Panels Solar Photovoltaics · Operational | — | 6.3 km |
Metrocentre Green Car Park, St Michaels Way - Photovoltaic Equipment Solar Photovoltaics · Under Construction | — | 7.1 km |
Holmside Hall Wind Onshore · Operational | 2.8 | 7.8 km |
Unipres building Solar Photovoltaics · Operational | 4.9 | 7.8 km |
Nissan Motors Plant Extn Wind Onshore · Operational | 2 | 8 km |
How big is Kibblesworth Landfill Site?
Kibblesworth Landfill Site has a recorded installed capacity of 2.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Kibblesworth Landfill Site?
REPD records the operator as SITA UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Kibblesworth Landfill Site approved and built?
The application was submitted on 1996-12-24. Permission was granted on 1998-06-05, 17 months later. The site became operational on 1998-10-26, 5 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 565.
Novarly Parcel · official public data, read properly · parcel.novarly.com