Unipres building
Unipres building is an operational 4.9 MW solar farm in Sunderland, generating since 31 July 2020. Planning permission was granted on 14 February 2019, 2 months after submission. Operator of record: Regenerco.
Planning and build timeline
| Application submitted | 12 December 2018 |
| Permission granted | 14 February 2019 2 months after submission |
| Operational | 31 July 2020 18 months after consent |
Screening a site of your own?
Sunderland approves 92% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Unipres building’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Sunderland’s record on solar
Sunderland has decided 26 solar farms and approved 92%, taking a median of 1.9 months. See every solar farm decision in Sunderland →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 2 | 0.5 km |
Wind Onshore · Operational | 4 | 0.5 km |
Solar Photovoltaics · Operational | 4.8 | 1.2 km |
Battery · Operational | 35 | 6.8 km |
Landfill Gas · Operational | 1 | 7.1 km |
Landfill Gas · Operational | 2 | 7.2 km |
Landfill Gas · Operational | 2 | 7.3 km |
Solar Photovoltaics · Under Construction | — | 7.4 km |
How big is Unipres building?
Unipres building has a recorded installed capacity of 4.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Unipres building?
REPD records the operator as Regenerco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Unipres building approved and built?
The application was submitted on 12 December 2018. Permission was granted on 14 February 2019, 2 months later. The site became operational on 31 July 2020, 18 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7210.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode