Cattlegate Farm Biogas (Farm AD) is operational in Welwyn Hatfield with a recorded capacity of 1.5 MW, and has been generating since 2015-12-01.

1.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-12-01
Anaerobic Digestion
Technology
Willen Biogas & Xergi
Welwyn Hatfield
Authority
England

Planning and build timeline

Application submitted2011-08-24
Permission granted2013-06-20
22 months after submission
Operational2015-12-01
29 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Potters Bar Solar Farm
Solar Photovoltaics · Operational
56.6 km
Lockfield Avenue Solar
Solar Photovoltaics · Under Construction
0.27.1 km
Waltham Point Distribution Centre
Solar Photovoltaics · Operational
1.87.3 km
Land At Swanland Road
Solar Photovoltaics · Operational
57.6 km
Blanche Lane, South Mimms - Solar Panels
Solar Photovoltaics · Under Construction
0.619 km
Deephams Sewerage Treatment Works
Anaerobic Digestion · Operational
39.1 km
Tollgate Farm Battery Storage
Battery · Under Construction
49.59.7 km
Edmonton EcoPark EfW
EfW Incineration · Operational
5510.1 km

How big is Cattlegate Farm Biogas (Farm AD)?

Cattlegate Farm Biogas (Farm AD) has a recorded installed capacity of 1.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cattlegate Farm Biogas (Farm AD)?

REPD records the operator as Willen Biogas & Xergi. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cattlegate Farm Biogas (Farm AD) approved and built?

The application was submitted on 2011-08-24. Permission was granted on 2013-06-20, 22 months later. The site became operational on 2015-12-01, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 342.