Novarly ParcelRenewable sites

Renewable sitesPrinces Gate Spring Water

Princes Gate Spring Water

Princes Gate Spring Water is operational in Pembrokeshire with a recorded capacity of 1.6 MW, and has been generating since 2014-09-03.

1.6 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-09-03
Wind Onshore
Technology
Princes Gate Spring Water
Pembrokeshire
Authority
Wales

Planning and build timeline

Application submitted2011-11-18
Permission granted2013-07-09
20 months after submission
Operational2014-09-03
14 months after consent

Pembrokeshire’s record on onshore wind

Pembrokeshire has decided 15 onshore wind schemes and approved 47%, taking a median of 8 months. See every onshore wind scheme decision in Pembrokeshire

Other built sites within 15 km

SiteMWDistance
Caeremlyn Solar Farm
Solar Photovoltaics · Operational
187.1 km
Langdon Mill
Anaerobic Digestion · Under Construction
17.4 km
Yerbeston Gate Farm
Solar Photovoltaics · Operational
6.18.1 km
Parc Cynog Extension
Wind Onshore · Operational
8.410.5 km
Parc Cynog
Solar Photovoltaics · Operational
510.5 km
Parc-Cynog Wind Farm
Wind Onshore · Operational
3.610.8 km
Land West of Roberts Wall Far
Solar Photovoltaics · Operational
2.512 km
Jordanston Solar Farm
Solar Photovoltaics · Operational
513.2 km

How big is Princes Gate Spring Water?

Princes Gate Spring Water has a recorded installed capacity of 1.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Princes Gate Spring Water?

REPD records the operator as Princes Gate Spring Water. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Princes Gate Spring Water approved and built?

The application was submitted on 2011-11-18. Permission was granted on 2013-07-09, 20 months later. The site became operational on 2014-09-03, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3378.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council