Renewable sites › Princes Gate Spring Water
Princes Gate Spring Water
Princes Gate Spring Water is operational in Pembrokeshire with a recorded capacity of 1.6 MW, and has been generating since 2014-09-03.
Planning and build timeline
| Application submitted | 2011-11-18 |
| Permission granted | 2013-07-09 20 months after submission |
| Operational | 2014-09-03 14 months after consent |
Pembrokeshire’s record on onshore wind
Pembrokeshire has decided 15 onshore wind schemes and approved 47%, taking a median of 8 months. See every onshore wind scheme decision in Pembrokeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Caeremlyn Solar Farm Solar Photovoltaics · Operational | 18 | 7.1 km |
Langdon Mill Anaerobic Digestion · Under Construction | 1 | 7.4 km |
Yerbeston Gate Farm Solar Photovoltaics · Operational | 6.1 | 8.1 km |
Parc Cynog Extension Wind Onshore · Operational | 8.4 | 10.5 km |
Parc Cynog Solar Photovoltaics · Operational | 5 | 10.5 km |
Parc-Cynog Wind Farm Wind Onshore · Operational | 3.6 | 10.8 km |
Land West of Roberts Wall Far Solar Photovoltaics · Operational | 2.5 | 12 km |
Jordanston Solar Farm Solar Photovoltaics · Operational | 5 | 13.2 km |
How big is Princes Gate Spring Water?
Princes Gate Spring Water has a recorded installed capacity of 1.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Princes Gate Spring Water?
REPD records the operator as Princes Gate Spring Water. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Princes Gate Spring Water approved and built?
The application was submitted on 2011-11-18. Permission was granted on 2013-07-09, 20 months later. The site became operational on 2014-09-03, 14 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3378.
Novarly Parcel · official public data, read properly · parcel.novarly.com