Langdon Mill

Langdon Mill is under construction in Pembrokeshire with a recorded capacity of 1 MW.

1 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Anaerobic Digestion
Technology
Langdon Enterprises
Pembrokeshire
Authority
Wales

Planning and build timeline

Application submitted2015-08-03
Permission granted2015-12-11
4 months after submission
Operationalnot recorded

Other built sites within 15 km

SiteMWDistance
Yerbeston Gate Farm
Solar Photovoltaics · Operational
6.12 km
Jordanston Solar Farm
Solar Photovoltaics · Operational
56.8 km
Land West of Roberts Wall Far
Solar Photovoltaics · Operational
2.57.3 km
Princes Gate Spring Water
Wind Onshore · Operational
1.67.4 km
West Farm, Cosheston - Solar Farm
Solar Photovoltaics · Under Construction
99.6 km
West Farm (Solar)
Solar Photovoltaics · Operational
7.79.7 km
Golden Hill
Solar Photovoltaics · Operational
6.210.8 km
Oak Cottage
Solar Photovoltaics · Operational
4.911.6 km

How big is Langdon Mill?

Langdon Mill has a recorded installed capacity of 1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Langdon Mill?

REPD records the operator as Langdon Enterprises. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Langdon Mill approved and built?

The application was submitted on 2015-08-03. Permission was granted on 2015-12-11, 4 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5747.