Renewable sites › Land West of Roberts Wall Far
Land West of Roberts Wall Far
Land West of Roberts Wall Far is an operational 2.5 MW solar farm in Pembrokeshire, generating since 23 March 2016. Planning permission was granted on 26 June 2015, 4 months after submission. Operator of record: Navitas Project.
Planning and build timeline
| Application submitted | 17 February 2015 |
| Permission granted | 26 June 2015 4 months after submission |
| Operational | 23 March 2016 9 months after consent |
Screening a site of your own?
Pembrokeshire approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Land West of Roberts Wall Far’s recorded coordinate — swap in your own postcode or coordinates.
Pembrokeshire’s record on solar
Pembrokeshire has decided 30 solar farms and approved 100%, taking a median of 4.6 months. See every solar farm decision in Pembrokeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 5 | 3.5 km |
Anaerobic Digestion · Under Construction | 1 | 7.3 km |
Solar Photovoltaics · Operational | 6.1 | 9.1 km |
Solar Photovoltaics · Under Construction | 9 | 10.9 km |
Solar Photovoltaics · Operational | 7.7 | 11.1 km |
Solar Photovoltaics · Operational | 6.2 | 11.3 km |
Wind Onshore · Operational | 1.6 | 12 km |
Solar Photovoltaics · Operational | 8 | 14.3 km |
How big is Land West of Roberts Wall Far?
Land West of Roberts Wall Far has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land West of Roberts Wall Far?
REPD records the operator as Navitas Project. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land West of Roberts Wall Far approved and built?
The application was submitted on 17 February 2015. Permission was granted on 26 June 2015, 4 months later. The site became operational on 23 March 2016, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5019.