Novarly ParcelRenewable sites

Renewable sitesLand West of Roberts Wall Far

Land West of Roberts Wall Far

Land West of Roberts Wall Far is operational in Pembrokeshire with a recorded capacity of 2.5 MW, and has been generating since 2016-03-23.

2.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2016-03-23
Solar Photovoltaics
Technology
Navitas Project
Pembrokeshire
Authority
Wales

Planning and build timeline

Application submitted2015-02-17
Permission granted2015-06-26
4 months after submission
Operational2016-03-23
9 months after consent

Pembrokeshire’s record on solar

Pembrokeshire has decided 30 solar farms and approved 100%, taking a median of 4.6 months. See every solar farm decision in Pembrokeshire

Other built sites within 15 km

SiteMWDistance
Jordanston Solar Farm
Solar Photovoltaics · Operational
53.5 km
Langdon Mill
Anaerobic Digestion · Under Construction
17.3 km
Yerbeston Gate Farm
Solar Photovoltaics · Operational
6.19.1 km
West Farm, Cosheston - Solar Farm
Solar Photovoltaics · Under Construction
910.9 km
West Farm (Solar)
Solar Photovoltaics · Operational
7.711.1 km
Golden Hill
Solar Photovoltaics · Operational
6.211.3 km
Princes Gate Spring Water
Wind Onshore · Operational
1.612 km
Chapel Hill
Solar Photovoltaics · Operational
814.3 km

How big is Land West of Roberts Wall Far?

Land West of Roberts Wall Far has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Land West of Roberts Wall Far?

REPD records the operator as Navitas Project. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Land West of Roberts Wall Far approved and built?

The application was submitted on 2015-02-17. Permission was granted on 2015-06-26, 4 months later. The site became operational on 2016-03-23, 9 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5019.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council