Renewable sites › Land West of Roberts Wall Far
Land West of Roberts Wall Far
Land West of Roberts Wall Far is operational in Pembrokeshire with a recorded capacity of 2.5 MW, and has been generating since 2016-03-23.
Planning and build timeline
| Application submitted | 2015-02-17 |
| Permission granted | 2015-06-26 4 months after submission |
| Operational | 2016-03-23 9 months after consent |
Pembrokeshire’s record on solar
Pembrokeshire has decided 30 solar farms and approved 100%, taking a median of 4.6 months. See every solar farm decision in Pembrokeshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Jordanston Solar Farm Solar Photovoltaics · Operational | 5 | 3.5 km |
Langdon Mill Anaerobic Digestion · Under Construction | 1 | 7.3 km |
Yerbeston Gate Farm Solar Photovoltaics · Operational | 6.1 | 9.1 km |
West Farm, Cosheston - Solar Farm Solar Photovoltaics · Under Construction | 9 | 10.9 km |
West Farm (Solar) Solar Photovoltaics · Operational | 7.7 | 11.1 km |
Golden Hill Solar Photovoltaics · Operational | 6.2 | 11.3 km |
Princes Gate Spring Water Wind Onshore · Operational | 1.6 | 12 km |
Chapel Hill Solar Photovoltaics · Operational | 8 | 14.3 km |
How big is Land West of Roberts Wall Far?
Land West of Roberts Wall Far has a recorded installed capacity of 2.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Land West of Roberts Wall Far?
REPD records the operator as Navitas Project. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Land West of Roberts Wall Far approved and built?
The application was submitted on 2015-02-17. Permission was granted on 2015-06-26, 4 months later. The site became operational on 2016-03-23, 9 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5019.
Novarly Parcel · official public data, read properly · parcel.novarly.com