Renewable sitesParc Cynog

Parc Cynog

Parc Cynog is an operational 5 MW solar farm in Carmarthenshire, generating since 24 March 2016. Planning permission was granted on 10 November 2015, 3 months after submission. Operator of record: Vattenfall.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 24 March 2016
Solar Photovoltaics
Technology
Vattenfall
Carmarthenshire
Authority
Wales

Planning and build timeline

Application submitted10 August 2015
Permission granted10 November 2015
3 months after submission
Operational24 March 2016
4 months after consent

Screening a site of your own?

RedlineUK · £39

Carmarthenshire approves 93% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Parc Cynog’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Carmarthenshire’s record on solar

Carmarthenshire has decided 28 solar farms and approved 93%, taking a median of 4.8 months. See every solar farm decision in Carmarthenshire

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
8.40 km
Wind Onshore · Operational
3.60.4 km
Solar Photovoltaics · Operational
1810.3 km
Wind Onshore · Operational
1.610.5 km

How big is Parc Cynog?

Parc Cynog has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Parc Cynog?

REPD records the operator as Vattenfall. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Parc Cynog approved and built?

The application was submitted on 10 August 2015. Permission was granted on 10 November 2015, 3 months later. The site became operational on 24 March 2016, 4 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 5499.