Caeremlyn Solar Farm

Caeremlyn Solar Farm is operational in Carmarthenshire with a recorded capacity of 18 MW, and has been generating since 2014-03-31.

18 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-03-31
Solar Photovoltaics
Technology
Munich RE
Carmarthenshire
Authority
Wales

Planning and build timeline

Application submitted2012-05-31
Permission granted2013-01-14
7 months after submission
Operational2014-03-31
14 months after consent

Carmarthenshire’s record on solar

Carmarthenshire has decided 28 solar farms and approved 93%, taking a median of 4.8 months. See every solar farm decision in Carmarthenshire

Other built sites within 15 km

SiteMWDistance
Princes Gate Spring Water
Wind Onshore · Operational
1.67.1 km
Dyffryn Brodyn Wind Farm
Wind Onshore · Operational
5.59.7 km
Parc Cynog Extension
Wind Onshore · Operational
8.410.3 km
Parc Cynog
Solar Photovoltaics · Operational
510.3 km
Parc-Cynog Wind Farm
Wind Onshore · Operational
3.610.7 km
Langdon Mill
Anaerobic Digestion · Under Construction
114.2 km
Yerbeston Gate Farm
Solar Photovoltaics · Operational
6.114.3 km

How big is Caeremlyn Solar Farm?

Caeremlyn Solar Farm has a recorded installed capacity of 18 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Caeremlyn Solar Farm?

REPD records the operator as Munich RE. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Caeremlyn Solar Farm approved and built?

The application was submitted on 2012-05-31. Permission was granted on 2013-01-14, 7 months later. The site became operational on 2014-03-31, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1719.