Pillswood Phase 2
Pillswood Phase 2 is operational in East Riding of Yorkshire with a recorded capacity of 49.5 MW, and has been generating since 2022-11-01.
Planning and build timeline
| Application submitted | 2019-05-23 |
| Permission granted | 2023-07-25 50 months after submission |
| Operational | 2022-11-01 |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Riding of Yorkshire’s record on battery storage
East Riding of Yorkshire has decided 19 battery storage schemes and approved 95%, taking a median of 5.3 months. See every battery storage scheme decision in East Riding of Yorkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Pillswood Phase 1 Battery · Operational | 49.5 | 0.2 km |
Creyke Beck Battery · Operational | 49.9 | 0.5 km |
Cottingham - Solar Farm Solar Photovoltaics · Operational | 5 | 4.2 km |
Carlam Hill Education CIC Solar Photovoltaics · Operational | 5 | 6.7 km |
Samaritans Spring Bank Solar Panels Solar Photovoltaics · Operational | — | 7.3 km |
Energy Works (Hull) Advanced Conversion Technologies · Operational | 25 | 7.5 km |
Energy Works Hull - Wind Turbine Wind Onshore · Operational | 3 | 7.5 km |
Energy Works Hull - AD (Waste AD) Anaerobic Digestion · Operational | 3 | 7.5 km |
How big is Pillswood Phase 2?
Pillswood Phase 2 has a recorded installed capacity of 49.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Pillswood Phase 2?
REPD records the operator as Harmony Energy Storage. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Pillswood Phase 2 approved and built?
The application was submitted on 2019-05-23. Permission was granted on 2023-07-25, 50 months later. The site became operational on 2022-11-01.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7360.