Renewable sites › Pillswood Phase 2
Pillswood Phase 2
Pillswood Phase 2 is an operational 49.5 MW battery storage site in East Riding of Yorkshire, generating since 1 November 2022. Planning permission was granted on 25 July 2023, 50 months after submission. Operator of record: Harmony Energy Storage.
Planning and build timeline
| Application submitted | 23 May 2019 |
| Permission granted | 25 July 2023 50 months after submission |
| Operational | 1 November 2022 |
Screening a site of your own?
East Riding of Yorkshire approves 95% of battery storage schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Pillswood Phase 2’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Riding of Yorkshire’s record on battery storage
East Riding of Yorkshire has decided 19 battery storage schemes and approved 95%, taking a median of 5.3 months. See every battery storage scheme decision in East Riding of Yorkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Operational | 49.5 | 0.2 km |
Battery · Operational | 49.9 | 0.5 km |
Solar Photovoltaics · Operational | 5 | 4.2 km |
Solar Photovoltaics · Operational | 5 | 6.7 km |
Solar Photovoltaics · Operational | — | 7.3 km |
Advanced Conversion Technologies · Operational | 25 | 7.5 km |
Anaerobic Digestion · Operational | 3 | 7.5 km |
Wind Onshore · Operational | 3 | 7.5 km |
How big is Pillswood Phase 2?
Pillswood Phase 2 has a recorded installed capacity of 49.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Pillswood Phase 2?
REPD records the operator as Harmony Energy Storage. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Pillswood Phase 2 approved and built?
The application was submitted on 23 May 2019. Permission was granted on 25 July 2023, 50 months later. The site became operational on 1 November 2022.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7360.