Renewable sitesPillswood Phase 1

Pillswood Phase 1

Pillswood Phase 1 is operational in East Riding of Yorkshire with a recorded capacity of 49.5 MW, and has been generating since 2022-11-01.

49.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2022-11-01
Battery
Technology
Harmony Energy Storage
East Riding of Yorkshire
Authority
England

Planning and build timeline

Application submitted2017-04-06
Permission granted2018-10-30
19 months after submission
Operational2022-11-01
48 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Riding of Yorkshire’s record on battery storage

East Riding of Yorkshire has decided 19 battery storage schemes and approved 95%, taking a median of 5.3 months. See every battery storage scheme decision in East Riding of Yorkshire

Other built sites within 15 km

SiteMWDistance
Pillswood Phase 2
Battery · Operational
49.50.2 km
Creyke Beck
Battery · Operational
49.90.5 km
Cottingham - Solar Farm
Solar Photovoltaics · Operational
54.1 km
Carlam Hill Education CIC
Solar Photovoltaics · Operational
56.6 km
Samaritans Spring Bank Solar Panels
Solar Photovoltaics · Operational
7.2 km
Energy Works (Hull)
Advanced Conversion Technologies · Operational
257.3 km
Energy Works Hull - Wind Turbine
Wind Onshore · Operational
37.3 km
Energy Works Hull - AD (Waste AD)
Anaerobic Digestion · Operational
37.3 km

How big is Pillswood Phase 1?

Pillswood Phase 1 has a recorded installed capacity of 49.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pillswood Phase 1?

REPD records the operator as Harmony Energy Storage. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pillswood Phase 1 approved and built?

The application was submitted on 2017-04-06. Permission was granted on 2018-10-30, 19 months later. The site became operational on 2022-11-01, 48 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7005.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council