Renewable sites › Cottingham - Solar Farm
Cottingham - Solar Farm
Cottingham - Solar Farm is operational in East Riding of Yorkshire with a recorded capacity of 5 MW, and has been generating since 2022-02-01.
Planning and build timeline
| Application submitted | 2021-06-08 |
| Permission granted | 2022-03-14 9 months after submission |
| Operational | 2022-02-01 |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 2 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
East Riding of Yorkshire’s record on solar
East Riding of Yorkshire has decided 57 solar farms and approved 100%, taking a median of 2.2 months. See every solar farm decision in East Riding of Yorkshire →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Creyke Beck Battery · Operational | 49.9 | 3.7 km |
Pillswood Phase 1 Battery · Operational | 49.5 | 4.1 km |
Pillswood Phase 2 Battery · Operational | 49.5 | 4.2 km |
Samaritans Spring Bank Solar Panels Solar Photovoltaics · Operational | — | 6.9 km |
Energy Works (Hull) Advanced Conversion Technologies · Operational | 25 | 8 km |
Energy Works Hull - Wind Turbine Wind Onshore · Operational | 3 | 8 km |
Energy Works Hull - AD (Waste AD) Anaerobic Digestion · Operational | 3 | 8 km |
Melton Waste Park Wind Onshore · Operational | 5 | 8.1 km |
How big is Cottingham - Solar Farm?
Cottingham - Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Cottingham - Solar Farm?
REPD records the operator as Hull & East Yorkshire Hospitals NHS Trust. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Cottingham - Solar Farm approved and built?
The application was submitted on 2021-06-08. Permission was granted on 2022-03-14, 9 months later. The site became operational on 2022-02-01.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9179.