Novarly ParcelRenewable sites

Renewable sitesCottingham - Solar Farm

Cottingham - Solar Farm

Cottingham - Solar Farm is an operational 5 MW solar farm in East Riding of Yorkshire, generating since 1 February 2022. Planning permission was granted on 14 March 2022, 9 months after submission. Operator of record: Hull & East Yorkshire Hospitals NHS Trust.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 1 February 2022
Solar Photovoltaics
Technology
Hull & East Yorkshire Hospitals NHS Trust
East Riding of Yorkshire
Authority
England

Planning and build timeline

Application submitted8 June 2021
Permission granted14 March 2022
9 months after submission
Operational1 February 2022

Screening a site of your own?

RedlineUK · £39

East Riding of Yorkshire approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Cottingham - Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Riding of Yorkshire’s record on solar

East Riding of Yorkshire has decided 57 solar farms and approved 100%, taking a median of 2.2 months. See every solar farm decision in East Riding of Yorkshire

Other built sites within 15 km

SiteMWDistance
Battery · Operational
49.93.7 km
Battery · Operational
49.54.1 km
Battery · Operational
49.54.2 km
Solar Photovoltaics · Operational
6.9 km
Advanced Conversion Technologies · Operational
258 km
Anaerobic Digestion · Operational
38 km
Wind Onshore · Operational
38 km
Wind Onshore · Operational
58.1 km

How big is Cottingham - Solar Farm?

Cottingham - Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Cottingham - Solar Farm?

REPD records the operator as Hull & East Yorkshire Hospitals NHS Trust. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Cottingham - Solar Farm approved and built?

The application was submitted on 8 June 2021. Permission was granted on 14 March 2022, 9 months later. The site became operational on 1 February 2022.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9179.