Renewable sites › Samaritans Spring Bank Solar Panels
Samaritans Spring Bank Solar Panels
Samaritans Spring Bank Solar Panels is operational in Kingston upon Hull, City of, and has been generating since 2021-07-01.
Planning and build timeline
| Application submitted | 2020-12-07 |
| Permission granted | 2021-03-02 3 months after submission |
| Operational | 2021-07-01 4 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
- Conservation area — Spring Bank
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Kingston upon Hull, City of’s record on solar
Kingston upon Hull, City of has decided 23 solar farms and approved 100%, taking a median of 2.3 months. See every solar farm decision in Kingston upon Hull, City of →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Energy Works Hull - Wind Turbine Wind Onshore · Operational | 3 | 1.7 km |
Energy Works Hull - AD (Waste AD) Anaerobic Digestion · Operational | 3 | 1.7 km |
Energy Works (Hull) Advanced Conversion Technologies · Operational | 25 | 1.7 km |
King George Dock Biomass (dedicated) · Operational | 9 | 4.5 km |
Cottingham - Solar Farm Solar Photovoltaics · Operational | 5 | 6.9 km |
Carlam Hill Education CIC Solar Photovoltaics · Operational | 5 | 7 km |
Creyke Beck Battery · Operational | 49.9 | 7.2 km |
Pillswood Phase 1 Battery · Operational | 49.5 | 7.2 km |
How big is Samaritans Spring Bank Solar Panels?
REPD does not record an installed capacity for Samaritans Spring Bank Solar Panels.
Who operates Samaritans Spring Bank Solar Panels?
REPD records the operator as Samaritans of Kingston upon Hull. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Samaritans Spring Bank Solar Panels approved and built?
The application was submitted on 2020-12-07. Permission was granted on 2021-03-02, 3 months later. The site became operational on 2021-07-01, 4 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8182.