Samaritans Spring Bank Solar Panels

Samaritans Spring Bank Solar Panels is an operational solar farm in Kingston upon Hull, City of, generating since 1 July 2021. Planning permission was granted on 2 March 2021, 3 months after submission. Operator of record: Samaritans of Kingston upon Hull.

Capacity
as recorded in REPD
Operational
Status
since 1 July 2021
Solar Photovoltaics
Technology
Samaritans of Kingston upon Hull
Kingston upon Hull, City of
Authority
England

Planning and build timeline

Application submitted7 December 2020
Permission granted2 March 2021
3 months after submission
Operational1 July 2021
4 months after consent

Screening a site of your own?

RedlineUK · £39

Kingston upon Hull, City of approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Samaritans Spring Bank Solar Panels’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Kingston upon Hull, City of’s record on solar

Kingston upon Hull, City of has decided 23 solar farms and approved 100%, taking a median of 2.3 months. See every solar farm decision in Kingston upon Hull, City of

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
31.7 km
Advanced Conversion Technologies · Operational
251.7 km
Wind Onshore · Operational
31.7 km
Biomass (dedicated) · Operational
94.5 km
Solar Photovoltaics · Operational
56.9 km
Solar Photovoltaics · Operational
57 km
Battery · Operational
49.97.2 km
Battery · Operational
49.57.2 km

How big is Samaritans Spring Bank Solar Panels?

REPD does not record an installed capacity for Samaritans Spring Bank Solar Panels.

Who operates Samaritans Spring Bank Solar Panels?

REPD records the operator as Samaritans of Kingston upon Hull. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Samaritans Spring Bank Solar Panels approved and built?

The application was submitted on 7 December 2020. Permission was granted on 2 March 2021, 3 months later. The site became operational on 1 July 2021, 4 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8182.