Novarly ParcelRenewable sites

Renewable sitesEnergy Works (Hull)

Energy Works (Hull)

Energy Works (Hull) is an operational 25 MW advanced conversion plant in Kingston upon Hull, City of, generating since 1 March 2018. Planning permission was granted on 20 October 2011, 4 months after submission. Operator of record: Energy Works / The Spencer Group.

25 MW
Capacity
as recorded in REPD
Operational
Status
since 1 March 2018
Advanced Conversion Technologies
Technology
Energy Works / The Spencer Group
Kingston upon Hull, City of
Authority
England

Planning and build timeline

Application submitted27 June 2011
Permission granted20 October 2011
4 months after submission
Operational1 March 2018
76 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Kingston upon Hull, City of: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Energy Works (Hull)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
30 km
Anaerobic Digestion · Operational
30 km
Solar Photovoltaics · Operational
1.7 km
Biomass (dedicated) · Operational
93.6 km
Solar Photovoltaics · Operational
55.6 km
Solar Photovoltaics · Under Construction
25.76.2 km
Wind Onshore · Operational
1.76.3 km
Wind Onshore · Operational
1.36.4 km

How big is Energy Works (Hull)?

Energy Works (Hull) has a recorded installed capacity of 25 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Energy Works (Hull)?

REPD records the operator as Energy Works / The Spencer Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Energy Works (Hull) approved and built?

The application was submitted on 27 June 2011. Permission was granted on 20 October 2011, 4 months later. The site became operational on 1 March 2018, 76 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 919.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode