Renewable sitesEnergy Works Hull - AD (Waste AD)

Energy Works Hull - AD (Waste AD)

Energy Works Hull - AD (Waste AD) is operational in Kingston upon Hull, City of with a recorded capacity of 3 MW, and has been generating since 2018-03-01.

3 MW
Capacity
as recorded in REPD
Operational
Status
since 2018-03-01
Anaerobic Digestion
Technology
Energy Works / The Spencer Group
Kingston upon Hull, City of
Authority
England

Planning and build timeline

Application submitted2011-06-27
Permission granted2011-10-20
4 months after submission
Operational2018-03-01
76 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Energy Works (Hull)
Advanced Conversion Technologies · Operational
250 km
Energy Works Hull - Wind Turbine
Wind Onshore · Operational
30 km
Samaritans Spring Bank Solar Panels
Solar Photovoltaics · Operational
1.7 km
King George Dock
Biomass (dedicated) · Operational
93.6 km
Carlam Hill Education CIC
Solar Photovoltaics · Operational
55.6 km
Hull Solar Farm
Solar Photovoltaics · Under Construction
25.76.2 km
The Limes Wind Turbines
Wind Onshore · Operational
1.76.3 km
Saltend Wind Turbine
Wind Onshore · Operational
1.36.4 km

How big is Energy Works Hull - AD (Waste AD)?

Energy Works Hull - AD (Waste AD) has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Energy Works Hull - AD (Waste AD)?

REPD records the operator as Energy Works / The Spencer Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Energy Works Hull - AD (Waste AD) approved and built?

The application was submitted on 2011-06-27. Permission was granted on 2011-10-20, 4 months later. The site became operational on 2018-03-01, 76 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 290.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council