Renewable sites › Lumley Water Treatment Works - Solar Panels
Lumley Water Treatment Works - Solar Panels
Lumley Water Treatment Works - Solar Panels is operational in County Durham with a recorded capacity of 1.9 MW, and has been generating since 2022-01-21.
Planning and build timeline
| Application submitted | 2020-10-19 |
| Permission granted | 2020-12-18 2 months after submission |
| Operational | 2022-01-21 13 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
County Durham’s record on solar
County Durham has decided 46 solar farms and approved 93%, taking a median of 2 months. See every solar farm decision in County Durham →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Sedgeletch Sewage Treatment Works Solar Photovoltaics · Under Construction | — | 3.2 km |
Mark's Quarry Landfill Gas · Operational | 1 | 3.5 km |
Houghton-le-Spring Landfill Site Landfill Gas · Operational | 3 | 5.8 km |
PG4 St Bedes Power Generation (Extension 2) Landfill Gas · Operational | 1 | 6.4 km |
PG4 St Bedes Power Generation Landfill Gas · Operational | 2 | 6.5 km |
PG4 St Bedes Power Generation (Extension) Landfill Gas · Operational | 2 | 6.5 km |
Great Eppleton Wind Farm Wind Onshore · Operational | 3 | 7.4 km |
Great Eppleton Farm Repowering Wind Onshore · Operational | 8.2 | 7.4 km |
How big is Lumley Water Treatment Works - Solar Panels?
Lumley Water Treatment Works - Solar Panels has a recorded installed capacity of 1.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Lumley Water Treatment Works - Solar Panels?
REPD records the operator as Northumbrian Water Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Lumley Water Treatment Works - Solar Panels approved and built?
The application was submitted on 2020-10-19. Permission was granted on 2020-12-18, 2 months later. The site became operational on 2022-01-21, 13 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 10458.