Novarly ParcelRenewable sites

Renewable sitesPencoose Farm

Pencoose Farm

Pencoose Farm is an operational 8.5 MW solar farm in Cornwall, generating since 27 March 2015. Planning permission was granted on 24 October 2014, 3 months after submission. Operator of record: First Solar Project Ltd.

8.5 MW
Capacity
as recorded in REPD
Operational
Status
since 27 March 2015
Solar Photovoltaics
Technology
First Solar Project Ltd
Cornwall
Authority
England

Planning and build timeline

Application submitted25 July 2014
Permission granted24 October 2014
3 months after submission
Operational27 March 2015
5 months after consent

Screening a site of your own?

RedlineUK · £39

Cornwall approves 92% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Pencoose Farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on solar

Cornwall has decided 146 solar farms and approved 92%, taking a median of 3.3 months. See every solar farm decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
102.5 km
Solar Photovoltaics · Operational
8.93.3 km
Wind Onshore · Operational
1.73.6 km
Hot Dry Rocks (HDR) · Operational
33.6 km
Landfill Gas · Operational
24.4 km
Solar Photovoltaics · Operational
64.4 km
Landfill Gas · Operational
34.5 km
Solar Photovoltaics · Operational
1.35.1 km

How big is Pencoose Farm?

Pencoose Farm has a recorded installed capacity of 8.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Pencoose Farm?

REPD records the operator as First Solar Project Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Pencoose Farm approved and built?

The application was submitted on 25 July 2014. Permission was granted on 24 October 2014, 3 months later. The site became operational on 27 March 2015, 5 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2009.