Renewable sites › Roskrow Wind Turbines
Roskrow Wind Turbines
Roskrow Wind Turbines is operational in Cornwall with a recorded capacity of 1.7 MW, and has been generating since 2007-12-01.
Planning and build timeline
| Application submitted | 2002-12-01 |
| Permission granted | 2004-02-25 15 months after submission |
| Operational | 2007-12-01 45 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cornwall’s record on onshore wind
Cornwall has decided 35 onshore wind schemes and approved 74%, taking a median of 7.5 months. See every onshore wind scheme decision in Cornwall →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Roskrow Farm Solar Photovoltaics · Operational | 8.9 | 0.4 km |
Pencoose Farm Solar Photovoltaics · Operational | 8.5 | 3.6 km |
Carn Vean Wind Onshore · Operational | 10 | 4 km |
Nancrossa Farm solar park Solar Photovoltaics · Operational | 6 | 4.2 km |
LITTLE TREVEASE SOLAR PARK Solar Photovoltaics · Operational | 5.3 | 5.9 km |
Higher Tregarne Solar Farm Solar Photovoltaics · Operational | 5 | 6.2 km |
United Downs Project (Geothermal) Hot Dry Rocks (HDR) · Operational | 3 | 6.4 km |
Little White Alice Solar Park Solar Photovoltaics · Operational | 1.3 | 6.7 km |
How big is Roskrow Wind Turbines?
Roskrow Wind Turbines has a recorded installed capacity of 1.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Roskrow Wind Turbines?
REPD records the operator as REG Windpower (previously Cornwall Light and Power). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Roskrow Wind Turbines approved and built?
The application was submitted on 2002-12-01. Permission was granted on 2004-02-25, 15 months later. The site became operational on 2007-12-01, 45 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3233.