Renewable sites › Nancrossa Farm solar park
Nancrossa Farm solar park
Nancrossa Farm solar park is operational in Cornwall with a recorded capacity of 6 MW, and has been generating since 2016-03-31.
Planning and build timeline
| Application submitted | 2014-05-14 |
| Permission granted | 2015-09-08 16 months after submission |
| Operational | 2016-03-31 7 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Cornwall’s record on solar
Cornwall has decided 146 solar farms and approved 92%, taking a median of 3.3 months. See every solar farm decision in Cornwall →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
LITTLE TREVEASE SOLAR PARK Solar Photovoltaics · Operational | 5.3 | 2.1 km |
Carn Vean Wind Onshore · Operational | 10 | 2.2 km |
Little White Alice Solar Park Solar Photovoltaics · Operational | 1.3 | 3.2 km |
Roskrow Wind Turbines Wind Onshore · Operational | 1.7 | 4.2 km |
Roskrow Farm Solar Photovoltaics · Operational | 8.9 | 4.3 km |
Pencoose Farm Solar Photovoltaics · Operational | 8.5 | 4.4 km |
Higher Tregarne Solar Farm Solar Photovoltaics · Operational | 5 | 5.5 km |
United Downs Project (Geothermal) Hot Dry Rocks (HDR) · Operational | 3 | 8 km |
How big is Nancrossa Farm solar park?
Nancrossa Farm solar park has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Nancrossa Farm solar park?
REPD records the operator as Second Solar Project. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Nancrossa Farm solar park approved and built?
The application was submitted on 2014-05-14. Permission was granted on 2015-09-08, 16 months later. The site became operational on 2016-03-31, 7 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2126.