Carn Vean is an operational 10 MW onshore wind farm in Cornwall, generating since 30 October 2008. Planning permission was granted on 11 September 2008, 3 months after submission. Operator of record: Unknown.

10 MW
Capacity
as recorded in REPD
Operational
Status
since 30 October 2008
Wind Onshore
Technology
Unknown
Cornwall
Authority
England

Planning and build timeline

Application submitted26 June 2008
Permission granted11 September 2008
3 months after submission
Operational30 October 2008
2 months after consent

Screening a site of your own?

RedlineUK · £39

Cornwall approves 74% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Carn Vean’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Cornwall’s record on onshore wind

Cornwall has decided 35 onshore wind schemes and approved 74%, taking a median of 7.5 months. See every onshore wind scheme decision in Cornwall

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
62.2 km
Solar Photovoltaics · Operational
8.52.5 km
Solar Photovoltaics · Operational
1.32.9 km
Solar Photovoltaics · Operational
8.93.9 km
Wind Onshore · Operational
1.74 km
Solar Photovoltaics · Operational
5.34.2 km
Hot Dry Rocks (HDR) · Operational
36 km
Landfill Gas · Operational
36.6 km

How big is Carn Vean?

Carn Vean has a recorded installed capacity of 10 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Carn Vean?

REPD records the operator as Unknown. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Carn Vean approved and built?

The application was submitted on 26 June 2008. Permission was granted on 11 September 2008, 3 months later. The site became operational on 30 October 2008, 2 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3077.