Novarly ParcelRenewable planning

Renewable planning SolarCornwall

Solar planning in Cornwall

Cornwall has decided 146 solar farms and approved 92% of them, taking a median of 3.3 months to decide. Consented capacity: 732 MW. 13 applications still awaiting a decision.

92%
Approved
134 granted · 12 refused
3.3 mo
Median decision
UK 2.3 mo
732 MW
Consented
62 MW refused
21
Appeals
14 allowed on appeal

How Cornwall compares

Against the 298 UK authorities with 5+ solar decisions, Cornwall sits in the 31st percentile for approval rate (1 points below the England average) and the 24th percentile for speed.

Decisions by year

1530Approved — 3 (2010)3Approved — 29 (2011)2911Approved — 12 (2012)12Approved — 20 (2013)Refused — 3 (2013)2313Approved — 14 (2014)Refused — 3 (2014)17Approved — 8 (2015)Refused — 4 (2015)1215Approved — 2 (2016)2Approved — 1 (2020)120Approved — 2 (2021)2Approved — 13 (2022)1322Approved — 7 (2023)Refused — 1 (2023)8Approved — 14 (2024)1424Approved — 7 (2025)7Approved — 1 (2026)126
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (174)

SchemeMWStatusDecided
Menear Road - Solar & Battery storage
Anesco Limited · PA23/09532 · 23.3 mo to decide
17.51Awaiting Construction2026-02-13
Fair Park Solar Farm
Downing Renewable Developments Llp · PA23/02629 · 30 mo to decide
49.9Awaiting Construction2025-10-16
J Sainsbury, Treyew Road - Solar panels
Cornwall Council · PA25/06524 · 1.3 mo to decide
0.44Awaiting Construction2025-10-06
Bowood Golf Club, Bowood Park - Solar Panels
Bowood Park Golf Club · PA24/05445 · 13.5 mo to decide
0.19Awaiting Construction2025-09-24
Canworthy House, Canworthy Water - Solar Farm
Windel Energy / Canadian Solar · PA23/04306 · 26 mo to decide
42Awaiting Construction2025-08-19
Trevarthian Farmhouse - Solar PV Farm & Battery Energy Storage
Trevarthian Renewables Limited · PA25/04503
49.9Application Submitted2025-06-13
Watering Lane Nursery, Lobbs Shop - Solar PV Panels & Battery Storage System
Keystone Ventures International Limited · 25/00381/FUL · 3.4 mo to decide
Awaiting Construction2025-06-02
Pilgrims Pride Limited, Newtons Margate Industrial Estate -Solar Panels
EDF Energy Renewables Limited · PA24/09499 · 3 mo to decide
1.1Awaiting Construction2025-04-15
Loggans Roundabout, Loggans Road - Solar Farm
Bauer Group · PA24/02723 · 9.9 mo to decide
2.5Awaiting Construction2025-02-17
Nic Ice, Bodmin Business Park - Solar Panels
Clearvolt & Nic Ice Limited · PA24/08486 · 1.5 mo to decide
0.57Awaiting Construction2024-12-24
China Fleet Country Club - Solar Array
China Fleet Club · PA24/07255 · 2.3 mo to decide
0.6Awaiting Construction2024-12-18
Woodland Barton Farm -Solar Farm
KPS SPV 4 Limited · PA24/07060 · 1.2 mo to decide
4.5Awaiting Construction2024-11-01
Vospers, Treliske Retail Park - Solar Panels
Vospers Motor House Limited · PA24/06725 · 1.8 mo to decide
Awaiting Construction2024-10-24
China Fleet Country Club, Pill Lane - Solar Array
China Fleet Club · PA24/07255
0.6Application Submitted2024-10-08
Green Acres Farm, Scarcewater - Solar Farm
EDF Renewables · PA24/05312
49.9Application Submitted2024-08-13
Pilgrim Factory Car Park And Fields, Cooksland Road - Solar Carport
Envams Limited · PA24/04140 · 1.8 mo to decide
1.2Awaiting Construction2024-07-19
Copper Bottom Solar Farm Ground-Mounted Solar PV Array
Aura Power Storage Solutions · PA22/06139 · 23.7 mo to decide
30Awaiting Construction2024-07-18
The Cornwall Hotel Spa & Estate - Solar Array & Battery Storage
Belle Isle Hotels (Cornwall) Limited · PA24/04534
0.63Application Submitted2024-07-16
Healeys Cornish Cyder - Solar Panels
Healeys Cornish Cyder · PA24/04583 · 1.1 mo to decide
0.53Awaiting Construction2024-07-15
Connon Bridge - Solar Array
Cornwall Council · PA23/10265 · 5.8 mo to decide
0.9Awaiting Construction2024-07-09
Cornwall Gateway Trunk Road, Service Area - Solar Farm
Gridserve Sustainable Energy Limited · PA23/05639 · 10.4 mo to decide
0.85Awaiting Construction2024-06-20
Watson Marlow, Bickland Water Road - Solar Pv Panels
Watson Marlow Limited/Bio Pure Technology · PA24/02925 · 2.3 mo to decide
0.34Awaiting Construction2024-06-18
Sir Ben Ainslie Sports Centre, Trennick Lane - Solar Panels
Truro School · PA24/02476 · 1.3 mo to decide
0.24Awaiting Construction2024-05-20
Healeys, Cyder Farm - Solar Photovoltaic Array
Healeys Cornish Cyder Farm · PA23/02391 · 10.6 mo to decide
0.75Awaiting Construction2024-03-12
Penbeagle Industrial Estate - Solar PV
Celtic Fish & Game · PA24/00552 · 0.9 mo to decide
0.16Awaiting Construction2024-02-27
Whalesborough Farm, Marhamchurch - Solar Array
Country Parks Limited · PA23/04788 · 7.2 mo to decide
2.1Awaiting Construction2024-02-23
The Coach House, Gwinear Lane - Speedwell Solar Farm
StatKraft · PA23/09696
40Application Submitted2024-01-22
Spinnaker International Spinnaker House, Long Acre - Solar Panels
Secure Innovation · PA23/08651 · 1.4 mo to decide
0.16Awaiting Construction2023-12-07
Tregonning Farm - Solar Farm & Battery Storage
Renewable Connections Developments Limited · PA22/01511 · 21.1 mo to decide
49.9Awaiting Construction2023-12-05
Roddas, The Creamery - Solar Photovoltaic Array
Roddas · PA23/00424 · 8 mo to decide
2.65Awaiting Construction2023-11-08
Par Market, Par Moor Road - Solar Array
Par Market · PA22/11426
0.5Application Withdrawn2023-11-01
Tolvaddon Business Park, Pool - Solar Array
Undercover Group · PA23/04674 · 1.7 mo to decide
0.43Awaiting Construction2023-08-25
Headland Hotel, Headland Road - Solar Panels
The Headland Hotel · PA22/11258 · 6.9 mo to decide
0.18Application Refused2023-08-03
Trevornick Holiday Park, Holywell Bay - Solar Array
Trevornick Holiday Park · PA23/00643 · 1.6 mo to decide
0.25Awaiting Construction2023-05-22
Burthy Row Farm, Trefullock Moor - Solar Farm & Battery Storage
JBM Solar Projects Limited · PA23/01893
49.9Application Submitted2023-03-22
Perransands Holiday Centre, Perransands Holiday Park - Solar PV Equipment
Bourne Leisure Limited · PA22/10938 · 2.1 mo to decide
0.53Awaiting Construction2023-02-10
Riviere Sands Holiday Park, Riviere Towans - Solar Panels
Bourne Leisure Group · PA22/11055 · 1.8 mo to decide
0.24Awaiting Construction2023-02-07
Trenake Farm, Pelynt - Solar PV Array
Trenake Manor Farm / Clean Earth Energy · PA22/08796 · 1.4 mo to decide
0.18Awaiting Construction2022-12-13
Morrisons, Priory Road - Solar Photovoltaic System
Morrisons · PA22/09227 · 1.8 mo to decide
0.27Awaiting Construction2022-12-07
Morrisons, Stucley Road - Solar Panels
Morrisons · PA22/09225 · 1.4 mo to decide
0.33Awaiting Construction2022-12-02
WM Morrison Supermarkets, Long Rock - Solar Panels
Morrisons · PA22/09226 · 1.4 mo to decide
0.33Awaiting Construction2022-11-30
Tregenna Castle Hotel - Solar panels
Tregenna Castle Hotel Limited · PA22/08582 · 2 mo to decide
0.2Awaiting Construction2022-11-29
Collon Barton, St Veep - Solar Arrays
Ethy Barton Farming Partnership · PA22/08499 · 2.5 mo to decide
0.15Awaiting Construction2022-11-24
Morrisons Superstore, Plymouth Road - Solar Photovoltaic System
Morrisons · PA22/09193 · 1 mo to decide
0.37Awaiting Construction2022-11-17
Pilgrim, Pool Industrial Estate - Solar Panels
EDF Energy Renewables · PA22/06419 · 1.6 mo to decide
0.82Awaiting Construction2022-08-30
Station Road, Kelly Bray - Solar Panel
Kb Products · PA22/06431 · 1.1 mo to decide
0.16Awaiting Construction2022-08-15
Treyew Road - Solar Panels
Carbon Neutral Cornwall Team · PA22/02718 · 1.8 mo to decide
0.33Awaiting Construction2022-05-30
Saputo Dairy UK
Lightsource BP · PA20/02612 · 23.9 mo to decide
4.2Operational2022-04-28
Treloggan Road - Solar Panels
WM Morrisons Supermarkets Plc · PA22/02030 · 1.6 mo to decide
0.37Awaiting Construction2022-04-13
Castle An Dinas Quarry, Ludgvan - Solar Array
Cornwall County Council · PA21/10585 · 4.2 mo to decide
0.4Awaiting Construction2022-03-25
Richard Lander School - Solar Photovoltaic Panels
Cornwall County Council · PA21/05270 · 1.7 mo to decide
0.48Awaiting Construction2021-11-04
Lidl Foodstore - Solar Panels
Lidl Great Britain · PA21/05975 · 2.4 mo to decide
0.18Operational2021-08-24
Tregorrick Farm
E H Energy Limited · PA20/11504
6Appeal Refused2021-01-13
Carland Cross - Solar Farm
Scottish Power Limited Payments and Supplier Services Department · PA19/08080 · 7 mo to decide
10Under Construction2020-05-26
HALVASSO - SOLAR FARM
Private Developer · PA12/09502 · 63 mo to decide
2.8Abandoned2018-01-11
Penhalurick Solar Farm
Solar Tech · PA15/02336 · 19.5 mo to decide
5Abandoned2016-11-21
Lower Tregeen Farm
Powerquinn · PA15/11004 · 4 mo to decide
5Awaiting Construction2016-04-15
Delabole
Good Energy · PA15/08617 · 4.9 mo to decide
2Planning Permission Expired2016-02-26
Land at Boslandew Hill
Far West Solar · PA15/05386 · 5.7 mo to decide
1Appeal Refused2015-12-23
Land At Penstruthal Farm
Big 60 Million · PA15/06838 · 3.7 mo to decide
3Application Refused2015-12-18
Bunkers Hill
Mably Solar · PA15/05327 · 3.6 mo to decide
5Application Refused2015-09-28
Nancrossa Farm solar park
Second Solar Project · PA14/04493 · 15.8 mo to decide
6Operational2015-09-08
Land At Bake Farm
Murex Energy · PA15/04793 · 2.4 mo to decide
5Operational2015-09-01
West Carclaze Solar Farm
Canadian Solar · PA15/03922 · 3 mo to decide
6.5Operational2015-08-28
Lower Ninestones Solar Farm
Clean Earth Energy · PA15/03935 · 3 mo to decide
2Abandoned2015-08-28
Hornacott Solar Park
Lightsource Renewable Energy · PA15/03083 · 2.1 mo to decide
5Appeal Refused2015-06-05
Newton Margate
Tulip Meats · PA14/11690 · 2.1 mo to decide
1.5Operational2015-05-22
Land North East Of Penrose Far
Clean Earth Energy · PA14/12025 · 3.8 mo to decide
1.5Operational2015-05-15
Bodwen Solar Park
Greencoat Capital · PA13/03710 · 22 mo to decide
5.5Operational2015-03-24
Carnemough Farm Solar Park
Elgin Energy EsCo · PA13/06755 · 18.5 mo to decide
7Operational2015-02-27
Mendennick Farm
REG Solarpower · PA14/11090 · 2.6 mo to decide
2.8Operational2015-02-13
Margate Solar Farm
Lanhydrock Estate Company · PA14/08958 · 2.4 mo to decide
3Operational2014-12-22
Villaton Farm Solar Park
Lightsource Renewable Energy · PA14/08272 · 3.3 mo to decide
12.5Application Refused2014-12-19
Hornacott Solar Park
Lightsource Renewable Energy · PA14/08270 · 3.3 mo to decide
29Revised2014-12-19
Anthony Estate Solar Farm
St Anthony 101 PV Park Ltd · PA14/06879 · 4.6 mo to decide
4.7Operational2014-12-17
Roskrow Farm
Roskrow Solar · PA14/08288 · 1.8 mo to decide
8.9Operational2014-11-24
Northmoor
Lightsource Renewable Energy · PA14/08271 · 2.3 mo to decide
5Operational2014-11-21
Pencoose Farm
First Solar Project Ltd · PA14/07019 · 3 mo to decide
8.5Operational2014-10-24
Treswarrow Solar Park
Private Developer · PA13/04287 · 17.1 mo to decide
6.5Operational2014-10-20
Southdown Quarry
Ethical Power · PA14/06734 · 2.8 mo to decide
1.5Operational2014-10-09
West Ditchen Farm
PV Sunpower Ltd · PA12/02141 · 31 mo to decide
5Operational2014-10-03
Burthy Farm
Elgin Energy EsCo · PA13/05983 · 14.6 mo to decide
10Operational2014-09-30
Mendennick Farm
REG Solarpower · PA14/04646 · 3.6 mo to decide
3Revised2014-09-26
Newton Ferrers solar park
Gruene Energien · PA14/04185 · 2.8 mo to decide
19.5Operational2014-08-01
Butteriss Solar Park
Antigua Solar · PA13/11664 · 5.2 mo to decide
3Appeal Refused2014-06-30
Kellygreen Farm
INRG Solar · PA13/07973 · 9.7 mo to decide
4Operational2014-06-23
Anthony Estate Solar Farm
St Anthony 101 PV Park Ltd · PA13/11705 · 5.4 mo to decide
9.8Revised2014-06-06
Trethosa Farm Solar Park
Trethosa Solar Ltd · PA13/11191 · 4.2 mo to decide
4.8Operational2014-06-06
Creathorne Farm - Solar Farm - extension
Good Energy Generation · PA14/01919
2.2Application Withdrawn2014-06-04
Garvinack Farm Solar Park
Lumicity · PA13/10523 · 5.2 mo to decide
7Operational2014-05-23
Wilton Farm (pv)
Primrose Solar · PA12/11941 · 12.7 mo to decide
9.5Operational2014-01-30
Land At Woodlands Farm
Kronos Solar · PA12/12014 · 11.2 mo to decide
8Application Refused2014-01-02
Bunkers Hill
Private Developer · PA13/08286 · 3.3 mo to decide
6.2Revised2013-12-20
Lanyon Farm
Good Energy Generation · PA13/07812 · 2.7 mo to decide
12.8Appeal Withdrawn2013-11-25
Trendeal Solar Farm
Caledon Partners · PA13/06612 · 2.7 mo to decide
12Abandoned2013-10-29
Carloggas Farm Solar Park
Good Energy Generation · PA13/06288 · 3.4 mo to decide
8.3Operational2013-10-29
Creathorne Farm - Solar Farm
Good Energy Generation · PA13/00489 · 7.7 mo to decide
1.8Operational2013-09-03
Gover Farm Solar Park
Green Energy UK Direct Ltd · PA13/03890 · 2.8 mo to decide
8Operational2013-08-30
Dunstan Lodge solar farm
Bond Holdings Ltd · PA13/03583 · 3.3 mo to decide
8.5Application Refused2013-08-29
Trequite Farm solar park
Elgin Energy EsCo · PA13/04650 · 3 mo to decide
9.9Operational2013-08-22
Four Burrows Farm (Extension 2)
Renewable Energy Systems (RES) · PA13/01195 · 4.6 mo to decide
6.3Operational2013-07-09
Hendra Barns Solar Farm
Caledon Partners (Smarter Energy Solutions Ltd) · PA13/02466 · 3.6 mo to decide
15Planning Permission Expired2013-07-08
Hexworthy Solar Park
Lightsource Renewable Energy · PA13/03036 · 2.9 mo to decide
5.4Abandoned2013-07-08
Trehawke Barton (Doddycross) Solar Farm
Foresight · PA12/11024 · 6.9 mo to decide
10.6Operational2013-06-21
Rew Farm Solar Farm
Lightsource Renewable Energy · PA12/08097 · 9.4 mo to decide
6.1Operational2013-06-10
Bodrawl Farm Solar Park
Kinetic Energy Ltd · PA13/03107
7.5Application Withdrawn2013-06-07
Trequite Farm
Elgin Energy EsCo · PA13/02242
11.4Revised2013-05-23
Penare Farm Solar Farm
British Solar Renewables (formerly Solar Power Generation) · PA12/12106 · 3.9 mo to decide
11Operational2013-04-26
Bodmin 2 Solar Farm
Solar Securities Group · PA12/09057 · 6.5 mo to decide
5.3Operational2013-04-12
North Wayton Farm
KS SPV21 Ltd · PA12/09275 · 6 mo to decide
5Operational2013-04-09
Nanteague Farm
British Solar Renewables · PA14/06773 · 7 mo to decide
7.7Operational2013-04-09
Kerriers Solar Park
Kronos Solar · PA12/10939 · 1.9 mo to decide
9.6Operational2013-03-15
Pensipple Farm
Elgin Energy EsCo · PA12/04228 · 9.6 mo to decide
5Operational2013-03-06
Four Burrows Solar farm (Extension 1)
Inazin Power Ltd · PA12/02338 · 11.1 mo to decide
1.5Operational2013-03-01
Wheal Alfred Road Solar Farm
TGC Renewables · PA12/08856 · 4.5 mo to decide
3.5Operational2013-02-12
Parabel North Beer Solar Farm
35 Degrees · PA12/10520 · 3.2 mo to decide
6.8Operational2013-02-11
KERNICK MICA DAM - SOLAR FARM
Private Developer · PA12/07557 · 5.8 mo to decide
12Operational2013-01-31
Land At Lanthrone
Elgin Energy EsCo · PA12/05854 · 7.3 mo to decide
5Application Refused2013-01-29
Canworthy Water
Equitix · PA12/07626 · 5 mo to decide
41Operational2013-01-21
Lowertown Farm
MTS Trewidland Solar Ltd · PA12/07247 · 5 mo to decide
4.5Application Refused2013-01-14
Little White Alice Solar Park
Little White Alice Ltd · PA12/09881 · 1.1 mo to decide
1.3Operational2013-01-07
Trefinnick Farm
MTS Trefinnick Solar Ltd · PA12/07093 · 4.9 mo to decide
5Operational2012-12-21
Carines Farm Solar Array
Solar Securities Group Ltd · PA12/06913 · 4.8 mo to decide
1Operational2012-12-11
Trehane Farm
Lightsource Renewable Energy · PA12/03098
1.4Application Withdrawn2012-12-03
Trelay Farm
Lightsource Renewable Energy · PA12/02878
1.5Application Withdrawn2012-12-03
Tregassow Farm - Solar Modules
Private Developer · PA12/04244 · 5.8 mo to decide
6Operational2012-11-16
Summercourt Solar Farm (Glebe Farm)
Solar Securities Group Ltd · PA12/05890 · 4.2 mo to decide
1.1Operational2012-10-31
LITTLE TREVEASE SOLAR PARK
Private Developer · PA12/04124 · 4.4 mo to decide
5.3Operational2012-10-26
Winnards Perch Solar Farm
Solar Securities Group · PA12/05258 · 4.4 mo to decide
3.8Operational2012-10-26
Yew Tree Cottage
Lightsource Renewable Energy · PA12/09032
2.8Application Withdrawn2012-10-12
Clann Solar Farm
Lightsource Renewable Energy · PA12/02871 · 6.4 mo to decide
1.4Operational2012-10-05
Trew Farm
Lightsource Renewable Energy · PA12/02876 · 6.4 mo to decide
1.5Abandoned2012-10-05
Ford Farm Solar Farm
Ford Farm PV Scheme LLP · PA12/06666 · 2.7 mo to decide
5Operational2012-10-05
Tredinnick Fields
Kronos Solar · PA12/04998 · 3 mo to decide
5.8Operational2012-08-31
Hope Solar Farm
Hope Solar Park Ltd · PA12/00827 · 6.9 mo to decide
7.3Operational2012-08-30
Higher Trevartha Farm
Smarter Energy Solutions Ltd · PA12/01530 · 0 mo to decide
3Operational2012-08-01
Langunnett Solar Farm
Vogt Solar · PA12/02354 · 4.3 mo to decide
6.2Operational2012-07-30
Tinny Hall Solar Farm
Lightsource Renewable Energy · PA12/02869
1.5Application Withdrawn2012-04-24
West Ditchen Farm Solar
PV Sunpower Ltd · PA11/01581
5Revised2012-02-27
Callington Solar Farm
Inazin (Low Carbon Solar) · PA11/00774 · 7.6 mo to decide
6.4Operational2011-09-26
Land at Gilley's Mill Dam
NextEnergy Solar Fund · PA11/03436 · 2.6 mo to decide
5Operational2011-08-05
Yonder Netherton
AEE Renewables · PA11/01438 · 2.9 mo to decide
3.2Abandoned2011-08-01
HENDRA HOLIDAY PARK SOLAR FARM
Hendra Holiday Park · PA11/03163 · 3 mo to decide
1.2Operational2011-07-14
Trelow Farm
Low carbon Solar Partners · PA11/01577 · 4.1 mo to decide
1.6Operational2011-07-05
Lower Bodiniel Farm
Wardell Armstrong International Ltd · PA11/01747 · 2.9 mo to decide
5Operational2011-06-07
Ninnis Farm Solar
The Green Company · PA11/01432 · 3.2 mo to decide
5Operational2011-06-03
West Kingsmill Farm Solar Park
Inazin (previously Low carbon Solar Partners) · PA11/01235 · 3.4 mo to decide
1.6Operational2011-05-30
Hawksland Solar
Moser Baer · PA10/08667 · 4.8 mo to decide
3.1Operational2011-05-24
Goonhilly Downs - PV
Wardell Armstrong International Ltd · PA11/00559 · 3.8 mo to decide
4.5Operational2011-05-24
Grange Farm (Cornwall)
Vogt Solar · PA11/01592 · 2.7 mo to decide
5Operational2011-05-24
Middle Treworder Farm
Innogy (previously BELECTRIC Solar) · PA11/00777 · 3 mo to decide
5Operational2011-05-06
Trenouth Farm
Low Carbon Solar · PA11/00760 · 3.3 mo to decide
3.6Operational2011-05-05
Trevemper solar farm
The Green Company · PA11/00374 · 3.4 mo to decide
1.7Operational2011-05-02
St Columb Major Solar Farm
Inazin Solar (previoulsy owned by Low Carbon Solar) · PA11/00560 · 3 mo to decide
7Operational2011-04-28
Causilgey Solar Farm
China Sunergy · PA10/07837 · 4.7 mo to decide
5Operational2011-04-21
East Langford Farm
Low carbon Solar Partners · PA11/01139 · 2.1 mo to decide
5Operational2011-04-18
Chester Energy (East Woolley Farm)
Chester Energy (Eastcott) · PA10/08695 · 4 mo to decide
5Operational2011-04-18
Howton Farm
Low carbon Solar Partners · PA11/00311 · 3.1 mo to decide
4.4Operational2011-04-18
Higher Tregarne Solar Farm
John Laing Environmental Assets · PA11/00674 · 3 mo to decide
5Operational2011-04-18
Kernow Solar Farm
Cornwall Council Property Services · PA11/00498 · 2.7 mo to decide
5Operational2011-04-18
Manor Farm
Low carbon Solar Partners · PA11/00670 · 2.3 mo to decide
4.7Operational2011-04-14
Nanterrow Farm
Low carbon Solar Partners · PA11/00751 · 2.2 mo to decide
4.7Operational2011-04-14
Fiddlers Green Solar Farm
Low Carbon Solar UK (dissolved) · PA11/00380 · 2.5 mo to decide
4.7Revised2011-04-08
Chynoweth Farm
Low carbon Solar Partners · PA11/01510 · 1.2 mo to decide
2.9Operational2011-03-31
Hewas Solar Farm
Lightsource Renewable Energy · PA10/08675 · 1 mo to decide
5Operational2011-03-31
Four Burrows Solar farm
TRIG · PA10/07942 · 3 mo to decide
7.2Operational2011-03-03
Trenoweth Solar Farm
Kronos Solar · PA10/07114 · 3 mo to decide
2.5Operational2011-02-15
Woodlands Barton Solar Farm
Laurence Associates · PA10/07307 · 2.8 mo to decide
4.9Operational2011-02-04
Winsdon Farm
Primrose Solar · PA10/06811 · 3.1 mo to decide
5Operational2011-01-28
Trefullock Solar Farm
Bosch Solar Energy · PA10/06679 · 2.6 mo to decide
5Operational2011-01-07
Benbole Farm
Private Developer · PA10/04656 · 4.5 mo to decide
2Operational2010-12-20
Polmaugan Farm
Munich RE · PA10/05105 · 3 mo to decide
5Operational2010-11-17
Wheal Jane
Lightsource Renewable Energy · PA10/03993 · 2.9 mo to decide
1.4Operational2010-09-17
Roskilly's - Solar Farm
Roskilly's
0.21Operational

Does Cornwall approve solar farms?

Yes — of the 146 solar farms Cornwall has decided, 92% were approved (134 granted, 12 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Cornwall?

The median time from application to decision is 3.3 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Cornwall consented?

732 MW has been consented across 134 approved schemes, with 62 MW refused. A further 13 applications awaits a decision.

Other technologies in Cornwall

Battery storage in CornwallOnshore wind in Cornwall

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report