United Downs Project (Geothermal)
United Downs Project (Geothermal) is an operational 3 MW geothermal plant in Cornwall, generating since 1 June 2021. Planning permission was granted on 13 August 2010, 5 months after submission. Operator of record: Geothermal Engineering.
Planning and build timeline
| Application submitted | 8 March 2010 |
| Permission granted | 13 August 2010 5 months after submission |
| Operational | 1 June 2021 130 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Cornwall: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with United Downs Project (Geothermal)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Landfill Gas · Operational | 2 | 0.7 km |
Landfill Gas · Operational | 3 | 1.3 km |
Solar Photovoltaics · Operational | 1.4 | 3 km |
Solar Photovoltaics · Operational | 8.5 | 3.6 km |
Wind Onshore · Operational | 10 | 6 km |
Solar Photovoltaics · Operational | 8.9 | 6 km |
Wind Onshore · Operational | 1.7 | 6.4 km |
Wind Onshore · Operational | 4.5 | 6.7 km |
How big is United Downs Project (Geothermal)?
United Downs Project (Geothermal) has a recorded installed capacity of 3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates United Downs Project (Geothermal)?
REPD records the operator as Geothermal Engineering. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was United Downs Project (Geothermal) approved and built?
The application was submitted on 8 March 2010. Permission was granted on 13 August 2010, 5 months later. The site became operational on 1 June 2021, 130 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4693.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode